The following information relates to a project (task times are in weeks):
What is the probability that the project can be completed within 60 weeks? What is the probability that the project will take longer than 60 weeks?
What is the probability that the project can be completed within 60 weeks? What is the probability that the project will take longer than 60 weeks?Explanation
PERT:
PERT is the Project Evaluation an...