Exercise 40
The Texas Department of Transportation (TxDOT) is considering two designs for crash barriers along a reconstructed portion of I-10. Design 2B will cost $3 million to install and $135,000 per year to maintain. Design 4R will cost $3.7 million to install and $70,000 per year to maintain. Calculate the rate of return and determine which design is preferred if TxDOT uses a MARR of 6% per year and a 20-year project period.
Explanation
Verified
like image
like image

Given information:
• Cost of design 2B ...