Exercise 29
The benefits associated with a nuclear power plant cooling water filtration project located on the Ohio River are $10,000 per year forever, starting in year 1. The costs are $50,000 in year 0 and $50,000 at the end of year 2. Calculate the B/C ratio at i = 10% per year.
Explanation
Verified
like image
like image

Present worth of a perpetuity is blured image where ...