The general manager for Woodslome Appliance Company Plant #A14 in Mexico City has four independent projects that she can fund this year to improve surface durability on stainless steel products. The project costs and 18% per year PW values are as shown. What projects should be accepted if the budget limit is
a) no limit and b) $55,000
a) no limit and b) $55,000

Explanation
12.9 (a) Select projects 2, 3 ...