The Office of the Undersecretary of Defense periodically releases unit cost data for use in military construction programs. If the unit cost for a satellite communications center (with shielding and generator) is $496 per square foot, what would be the estimated cost of a 6000-square-foot building
Explanation
The formula to calculate cost using unit...