Exercise 71
The equipment required to place 160 cubic yards of concrete by experienced workers is two gasoline engine vibrators and one concrete pump. If the vibrators cost $76 per day and the concrete pump costs $580 per day, estimate
a) the cost of the equipment per cubic yard of concrete and b) the equipment cost for placing 56 cubic yards of concrete.