The equipment required to place 160 cubic yards of concrete by experienced workers is two gasoline engine vibrators and one concrete pump. If the vibrators cost $76 per day and the concrete pump costs $580 per day, estimate
a) the cost of the equipment per cubic yard of concrete and b) the equipment cost for placing 56 cubic yards of concrete.
a) the cost of the equipment per cubic yard of concrete and b) the equipment cost for placing 56 cubic yards of concrete.
Explanation
The formula to calculate cost using unit...