Edition 7ISBN: 978-0073376301 Exercise 47
The ENR construction cost index for New York City had a value of 12,381.40 in February 2007. For Pittsburgh and Atlanta, the values were 7341.32 and 4874.06, respectively. If a general contractor in Atlanta won construction jobs totaling $54.3 million, determine their equivalent total value in New York City.
Explanation
The formula to calculate cost at current...