In problem, how much will be produced in each of the 3 months?
problem
A company plans to produce 25,000 units in a 3-month period. The months have 22, 21, and 20 working days respectively. What should the average daily production be?
problem
A company plans to produce 25,000 units in a 3-month period. The months have 22, 21, and 20 working days respectively. What should the average daily production be?
Explanation
Production leveling: