Exercise 16
The opening backlog is 1100 units. Forecast demand is shown in the following. Calculate the weekly production for level production if the backlog is to be increased to 1200 units. The opening backlog is 1100 units. Forecast demand is shown in the following. Calculate the weekly production for level production if the backlog is to be increased to 1200 units.
Explanation
Verified
like image
like image

Backlog:
Backlog represents the quantit...