expand icon
book Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive cover

Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive

Edition 8ISBN: 978-0134156323
book Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive cover

Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive

Edition 8ISBN: 978-0134156323
Exercise 5
In the example given on page 47 earlier in the chapter, the MPS was unsatisfactory because there were poor inventory balances compared to the production plan. There was also a stockout for product C in periods 2 and 3. Revise the production plans for the three products to cut out or reduce these problems.
(Reference Example) In the example given on page 47 earlier in the chapter, the MPS was unsatisfactory because there were poor inventory balances compared to the production plan. There was also a stockout for product C in periods 2 and 3. Revise the production plans for the three products to cut out or reduce these problems.  (Reference Example)
Explanation
Verified
like image
like image

Revise the following production plan as ...