expand icon
book Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive cover

Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive

Edition 8ISBN: 978-0134156323
book Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive cover

Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive

Edition 8ISBN: 978-0134156323
Exercise 6
The Acme Widget Company makes widgets in two models, and the bottleneck operation is in work center 10. Following is the resource bill (in hours per part). The Acme Widget Company makes widgets in two models, and the bottleneck operation is in work center 10. Following is the resource bill (in hours per part).   The master production schedule for the next 5 weeks is   a. Using the resource bill and the master production schedule, calculate the number of hours required in work center 10 for each of the 5 weeks. Use the following table to record the required capacity on the work center.   b. If the available capacity at work station 10 is 260 hours per week, suggest possible ways of meeting the demand in week 3. The master production schedule for the next 5 weeks is The Acme Widget Company makes widgets in two models, and the bottleneck operation is in work center 10. Following is the resource bill (in hours per part).   The master production schedule for the next 5 weeks is   a. Using the resource bill and the master production schedule, calculate the number of hours required in work center 10 for each of the 5 weeks. Use the following table to record the required capacity on the work center.   b. If the available capacity at work station 10 is 260 hours per week, suggest possible ways of meeting the demand in week 3. a. Using the resource bill and the master production schedule, calculate the number of hours required in work center 10 for each of the 5 weeks. Use the following table to record the required capacity on the work center. The Acme Widget Company makes widgets in two models, and the bottleneck operation is in work center 10. Following is the resource bill (in hours per part).   The master production schedule for the next 5 weeks is   a. Using the resource bill and the master production schedule, calculate the number of hours required in work center 10 for each of the 5 weeks. Use the following table to record the required capacity on the work center.   b. If the available capacity at work station 10 is 260 hours per week, suggest possible ways of meeting the demand in week 3. b. If the available capacity at work station 10 is 260 hours per week, suggest possible ways of meeting the demand in week 3.
Explanation
Verified
like image
like image

Using resource bill and MPS calculate nu...

close menu
Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive
cross icon