Given the following master schedule, fill in the projected available and available to promise rows:
b. A customer wants an order of 100 in period 4. What can you tell him?
c. The customer from part (b) cancels his request, but then says he wants 120 in period 5. What do you tell him now?
d. Sales has requested that you add an MPS of 200 in period 9 to cover their needs for a sales promotion. What do you tell them and why?
e. What action (if any) should be taken in period 11? Why is it okay to take the action?
b. A customer wants an order of 100 in period 4. What can you tell him?
c. The customer from part (b) cancels his request, but then says he wants 120 in period 5. What do you tell him now?
d. Sales has requested that you add an MPS of 200 in period 9 to cover their needs for a sales promotion. What do you tell them and why?
e. What action (if any) should be taken in period 11? Why is it okay to take the action?
Explanation
Master Production Schedule (MPS) is used...
Introduction to Materials Management 8th Edition by Steve Chapman ,Tony Arnold ,Ann Gatewood ,Lloyd Clive
Why don’t you like this exercise?
Other Minimum 8 character and maximum 255 character