Omega Technology is starting production of a new supercomputer for use in large research universities. It has just completed the first unit, which took 120 labor hours to produce. Based on its experience, it estimates its learning percentage to be 80 percent. How many labor hours should it expect the second unit to require to manufacture?
Explanation
Assume that the second unit requires x l...