Consider the following three jobs that need to be run on two machines in sequence: A(3 1), B(2 2), and C(1 3), where the run times on the first and second machine are given in parenthesis. In what order should the jobs be run to minimize the total time to complete all three jobs?
Explanation
Verified
like image
like image

Johnson's Rule:
This rule is used for j...