Exercise 23
The critical path in a PERT chart represents: a. The sequencing of tasks
B) The most important tasks of the whole project
C) The longest path of tasks needed for project completion
D) The tasks that must be completed without errors
Explanation
Verified
like image
like image

a.
The sequencing o f tasks : PERT is th...