Service Management: Operations, Strategy, Information Technology 8th Edition by James Fitzsimmons,Mona Fitzsimmons,Sanjeev Bordoloi
Edition 8ISBN: 978-1259010651
Service Management: Operations, Strategy, Information Technology 8th Edition by James Fitzsimmons,Mona Fitzsimmons,Sanjeev Bordoloi
Edition 8ISBN: 978-1259010651 Exercise 6
The project network for building a garage is shown in Figure 16.11 and includes data on activity times and their deviations.
a. Develop a Monte Carlo simulation model that can be used to generate a distribution of project completion times (longest path from node 1 to 8).
b. Simulate 5 project completion experiences using random numbers from Appendix B. What is the expected project duration time?

a. Develop a Monte Carlo simulation model that can be used to generate a distribution of project completion times (longest path from node 1 to 8).
b. Simulate 5 project completion experiences using random numbers from Appendix B. What is the expected project duration time?

Explanation
a.
Random numbers are drawn for eac...
Service Management: Operations, Strategy, Information Technology 8th Edition by James Fitzsimmons,Mona Fitzsimmons,Sanjeev Bordoloi
Why don’t you like this exercise?
Other Minimum 8 character and maximum 255 character
Character 255