expand icon
book Service Management: Operations, Strategy, Information Technology 8th Edition by James Fitzsimmons,Mona Fitzsimmons,Sanjeev Bordoloi cover

Service Management: Operations, Strategy, Information Technology 8th Edition by James Fitzsimmons,Mona Fitzsimmons,Sanjeev Bordoloi

Edition 8ISBN: 978-1259010651
book Service Management: Operations, Strategy, Information Technology 8th Edition by James Fitzsimmons,Mona Fitzsimmons,Sanjeev Bordoloi cover

Service Management: Operations, Strategy, Information Technology 8th Edition by James Fitzsimmons,Mona Fitzsimmons,Sanjeev Bordoloi

Edition 8ISBN: 978-1259010651
Exercise 17
2. The elapsed time for delivery of the hardware is estimated at 90 days. Would the project completion time be affected if delivery of the hardware were delayed by 30 days? Would the critical path change ?
Explanation
Verified
like image
like image

If the delivery of hardware were delayed...