
Service Management: Operations, Strategy, Information Technology 8th Edition by James Fitzsimmons,Mona Fitzsimmons,Sanjeev Bordoloi
Edition 8ISBN: 978-1259010651
Service Management: Operations, Strategy, Information Technology 8th Edition by James Fitzsimmons,Mona Fitzsimmons,Sanjeev Bordoloi
Edition 8ISBN: 978-1259010651 Exercise 5
A simple network consisting of four activities has the following network diagram:
The cost/time relationships for the activities are shown in the table below:
For example, if completed in 5 weeks, activity A would require $85,000, and if completed in 10 weeks, it would require $70,000.
a. What would be the minimum cost of completing this project in 20 weeks?
b. If the desired completion date is 33 weeks and the profit markup is 20 percent above cost, what should be the bid price for this project?

The cost/time relationships for the activities are shown in the table below:

For example, if completed in 5 weeks, activity A would require $85,000, and if completed in 10 weeks, it would require $70,000.
a. What would be the minimum cost of completing this project in 20 weeks?
b. If the desired completion date is 33 weeks and the profit markup is 20 percent above cost, what should be the bid price for this project?
Explanation
(a) Step 1 reduce C by 5 weeks, critical...
Service Management: Operations, Strategy, Information Technology 8th Edition by James Fitzsimmons,Mona Fitzsimmons,Sanjeev Bordoloi
Why don’t you like this exercise?
Other Minimum 8 character and maximum 255 character
Character 255