expand icon
book Service Management: Operations, Strategy, Information Technology 8th Edition by James Fitzsimmons,Mona Fitzsimmons,Sanjeev Bordoloi cover

Service Management: Operations, Strategy, Information Technology 8th Edition by James Fitzsimmons,Mona Fitzsimmons,Sanjeev Bordoloi

Edition 8ISBN: 978-1259010651
book Service Management: Operations, Strategy, Information Technology 8th Edition by James Fitzsimmons,Mona Fitzsimmons,Sanjeev Bordoloi cover

Service Management: Operations, Strategy, Information Technology 8th Edition by James Fitzsimmons,Mona Fitzsimmons,Sanjeev Bordoloi

Edition 8ISBN: 978-1259010651
Exercise 16
The following activities are required for completing a project:
The following activities are required for completing a project:     a. Draw a network diagram of this project showing the activities and their expected duration times. b. What is the critical path and the expected completion time of the project? c. What is the probability of completing the project in 41 days or less?
a. Draw a network diagram of this project showing the activities and their expected duration times.
b. What is the critical path and the expected completion time of the project?
c. What is the probability of completing the project in 41 days or less?
Explanation
Verified
like image
like image

PERT and CPM:
In order to keep track of...