expand icon
book Service Management: Operations, Strategy, Information Technology 8th Edition by James Fitzsimmons,Mona Fitzsimmons,Sanjeev Bordoloi cover

Service Management: Operations, Strategy, Information Technology 8th Edition by James Fitzsimmons,Mona Fitzsimmons,Sanjeev Bordoloi

Edition 8ISBN: 978-1259010651
book Service Management: Operations, Strategy, Information Technology 8th Edition by James Fitzsimmons,Mona Fitzsimmons,Sanjeev Bordoloi cover

Service Management: Operations, Strategy, Information Technology 8th Edition by James Fitzsimmons,Mona Fitzsimmons,Sanjeev Bordoloi

Edition 8ISBN: 978-1259010651
Exercise 18
The project network and table below show the expected number of weeks to complete a series of activities and the corresponding variances:
The project network and table below show the expected number of weeks to complete a series of activities and the corresponding variances:         a. Determine the critical path and the earliest expected completion time. b. What is the probability of completing the project in 24 weeks or less?
The project network and table below show the expected number of weeks to complete a series of activities and the corresponding variances:         a. Determine the critical path and the earliest expected completion time. b. What is the probability of completing the project in 24 weeks or less?
a. Determine the critical path and the earliest expected completion time.
b. What is the probability of completing the project in 24 weeks or less?
Explanation
Verified
like image
like image

(a) blured image Critical Path Activities:...