Exercise 2
In order to plan for procurements, the project team uses a project document that includes a list of deliverables, acceptance criteria, project assumptions and constraints, and a description of the product, service or result. This document is called the_______
A) work breakdown structure (WBS)
B) project charter
C) project contract
D) project scope statement
Explanation