Source selection criteria from the Plan Procurement Management process might include all of these outputs except:
A) technical approach
B) financial capacity
C) expert judgment
D) risk
A) technical approach
B) financial capacity
C) expert judgment
D) risk
Explanation
It is the process of recording the procu...