A_______ analysis is a technique that results in a decision about whether particular work can best be accomplished by the project team, or should be purchased from external sources.
A) make-or-buy
B) SWOT
C) sensitivity
D) vendor
A) make-or-buy
B) SWOT
C) sensitivity
D) vendor
Explanation
A Make or buy analysis is a technique th...