Which of these is a proposal evaluation technique used for complex procurements, where source selection will be made based on seller responses to previously defined criteria?
A) Bidder conference
B) Weighting system
C) Independent estimates
D) Advertising
A) Bidder conference
B) Weighting system
C) Independent estimates
D) Advertising
Explanation
For all the suppliers to whom contractor...