The upper and lower ________ are often +/ ? 3 standard deviations (3 sigma) around a process mean (average).
A) specification limits
B) tolerances
C) thresholds
D) control limits
A) specification limits
B) tolerances
C) thresholds
D) control limits
Explanation
When the outputs are within control limi...