Exercise 4
The upper and lower ________ are often +/ ? 3 standard deviations (3 sigma) around a process mean (average).
A) specification limits
B) tolerances
C) thresholds
D) control limits
Explanation
Verified
like image
like image

When the outputs are within control limi...