Maintenance money for an athletic complex has been sought. Mr. Kendall, Athletic Director, would like to solicit a donation to cover all future expected maintenance costs for the building. These maintenance costs are expected to be $1 million each year for the first five years, $1.3 million each year for years 6 through 10, and $1.5 million each year after that. (The building has an indefinite service life.)
If the money is placed in an account that will pay 5% interest compounded annually, how large should the gift be
If the money is placed in an account that will pay 5% interest compounded annually, how large should the gift be
Explanation
Capitalized cost is defined as the prese...