Contemporary Engineering Economics 6th Edition by Chan Park
Edition 6ISBN: 978-0134105598
Contemporary Engineering Economics 6th Edition by Chan Park
Edition 6ISBN: 978-0134105598 Exercise 9
An executive from a large merchandising firm has called your vice president for production to get a price quote for an additional 100 units of a given product. The vice president has asked you to prepare a cost estimate. The number of hours required to produce a unit is 5. The average labor rate is $12 per hour. The materials cost $14 per unit. Overhead for an additional 100 units is estimated at 50% of the direct labor cost. If the company wants to have a 30% profit margin, what should be the unit price to quote
Explanation
In this question there are many concepts...
Contemporary Engineering Economics 6th Edition by Chan Park
Why don’t you like this exercise?
Other Minimum 8 character and maximum 255 character
Character 255