Liquidated Damages. Cuesport Properties, LLC, sold a condominium in Anne Arundel County, Maryland, to Critical Developments, LLC. As part of the sale, Cuesport agreed to build a wall between Critical Developments' unit and an adjacent unit within thirty days of closing. If Cuesport failed to do so, it was to pay $126 per day until completion. This was an estimate of the amount of rent that Critical Developments would lose until the wall was finished and the unit could be rented. Actual damages were otherwise difficult to estimate at the time of the contract. The wall was built on time, but without a county permit, and it did not comply with the county building code. Critical Developments did not modify the wall to comply with the code until 260 days after the date of the contract deadline for completion of the wall. Does Cuesport have to pay Critical Developments $126 for each of the 260 days? Explain. [Cuesport Properties, LLC v. Critical Developments, LLC, 209 Md.App. 607, 61 A.3d 91 (2013)] (See page 354.)
Explanation
Verified
like image
like image

Liquidated Damages.
C have to pay Criti...