Question
Approximately what percent of the project time line should be devoted to each of the activities listed below?
Planning ______
Analysis ______
Design ______
Coding ______
Testing ______
If you could expend more time in one activity,which would have the highest likelihood of improving software quality? Why?
Use Space or
up arrow
down arrow
to flip the card.
Question
What is "earned value analysis" as it relates to project scheduling?
Question
In software project scheduling work,what is a task (or activity)network?
Question
List 3 principles for scheduling software projects.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/4
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 34: Project Scheduling
1
Approximately what percent of the project time line should be devoted to each of the activities listed below?
Planning ______
Analysis ______
Design ______
Coding ______
Testing ______
If you could expend more time in one activity,which would have the highest likelihood of improving software quality? Why?
Planning 2-3%
Analysis 10-25%
Design 20-25%
Coding 15-20%
Testing 30-40%
Expend more time in design because design is the place where quality is built into a product.
2
What is "earned value analysis" as it relates to project scheduling?
Earned value is a measure of progress.It enables you to assess the "percent of completeness" of a project using quantitative analysis rather than rely on a gut feeling.
Final Exam Question
3
In software project scheduling work,what is a task (or activity)network?
A task network is a graphic representation depicting software engineering task dependencies and the workflow for a project.
4
List 3 principles for scheduling software projects.
Unlock Deck
Unlock for access to all 4 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 4 flashcards in this deck.