Deck 7: Managing Project Resources

Full screen (f)
exit full mode
Question
Under conditions of unlimited resources the critical path:

A)and the critical chain are equal.
B)is shorter than the critical chain.
C)is longer than the critical chain.
D)is not affected by the critical chain.
Use Space or
up arrow
down arrow
to flip the card.
Question
Any activity on the critical path:

A)contains total slack.
B)is called critical activity.
C)is represented in blue in Microsoft Project.
D)contains free slack.
Question
The elapsed time between start and finish of an activity is referred to as:

A)effort.
B)length.
C)duration.
D)time.
Question
The process used to determine the magnitude and criticality of schedule variations is called:

A)criticality assessment.
B)order- of- magnitude estimation.
C)performance measurement.
D)critical path model.
Question
The time an activity can be delayed without affecting the immediately following activity is called:

A)lag time.
B)free slack.
C)lead time.
D)total slack.
Question
All of the following are techniques for estimating activity duration EXCEPT:

A)psychometric estimating.
B)expert judgment.
C)reserve analysis.
D)analogous estimating.
Question
The actual time spent working on an activity, not accounting for any breaks, is called:

A)length.
B)time.
C)effort.
D)duration.
Question
________ is any form of network analysis where resource management issues drive scheduling decisions.

A)Resource management
B)Schedule leveling
C)Resource analysis
D)Resource leveling
Question
A ________ is a control system developed to outline the process for the evaluation and implementation of schedule changes.

A)schedule change control system
B)scope control system
C)project control system
D)schedule model control system
Question
The ________ is a dedicated part of the organization whose purpose is to focus on various aspects of project management and provide services to the rest of the organization along those dimensions.

A)project management office
B)project support office
C)project maintenance office
D)project management bureau
Question
A ________ contains data and information that are compiled and used in conjunction with manual methods or project management software to perform schedule network analysis and to generate the schedule.

A)project management plan
B)schedule repository
C)project workbook
D)schedule model
Question
The estimation of activities' durations based upon the duration of similar activities is called:

A)similarity estimating.
B)psychometric estimating.
C)parametric estimating.
D)analogous estimating.
Question
Dates imposed to meet some type of development deadline are called:

A)external dependencies.
B)imposed dates.
C)mandatory dates.
D)none of the above.
Question
The critical path in a network diagram illustrates the:

A)effect of accumulated slack.
B)longest time in which a project is completed.
C)importance of resource leveling.
D)shortest time in which a project can be completed.
Question
Hard data from specific activities carried out on previous projects that may be used to more accurately estimate resource needs is called:

A)expert judgment.
B)bottom- up estimating.
C)alternatives analysis.
D)published estimating data.
Question
The estimation based on the experience of one or more experts on the particular activity or project is called:

A)published estimating data.
B)expert judgment.
C)bottom- up estimating.
D)alternatives analysis.
Question
The sequence of activities:

A)can be determined without considering resources.
B)cannot be determined without considering resources.
C)can only be determine when considering resources.
D)none of the above.
Question
In information systems development projects, ________ would be (an)example(s)of capital resources.

A)the project manager
B)both the development platform and the technical platform the software resides on
C)the development platform
D)the technological platform the software resides on
Question
The time an activity can be delayed without affecting the overall completion date of a project is called:

A)lag time.
B)free slack.
C)total slack.
D)lead time.
Question
________ is an estimating technique in which trade- offs between the time needed, the resources invested, and the desired quality of the final deliverable are examined.

A)Alternatives analysis
B)Published estimating data
C)Expert judgment
D)Bottom- up estimating
Question
Managing resources should be considered:

A)during execution of a project.
B)during all stages of a project.
C)during initiation and planning of a project.
D)during control and close- out stages of a project.
Question
The longest path through a network diagram, considering both task dependencies and resource dependencies is called:

A)critical path.
B)resource chain,
C)critical chain.
D)resource path.
Question
All of the following are tools and techniques to estimate resources EXCEPT:

A)expert judgment.
B)activity- resource analysis.
C)bottom- up estimating.
D)alternative analysis.
Question
Crashing and fast- tracking are ________ techniques.

A)schedule adjustment
B)schedule compression
C)path adjustment
D)schedule shortening
Question
Inputs into the activity resource estimating process include:

A)process assets.
B)enterprise environmental factors.
C)outputs from prior stages of the project.
D)all of the above.
Question
________ is a technique that is used to estimate project duration when individual activity duration estimates are uncertain.

A)Likelihood procedure
B)Three- point estimate
C)OPR- method
D)PERT
Question
________ use a process of evaluating alternative strategies by observing how changes to selected factors affect other factors and outcomes.

A)What- if analyses
B)Monaco analyses
C)If- then analyses
D)Monte Carlo analyses
Question
Resources:

A)affect both the time and the cost of a project.
B)do not affect a project much.
C)affect the time to complete a project.
D)affect the cost of a project.
Question
________ is a technique used to establish contingency reserves during a project to guard against potential risks.

A)Reserve analysis
B)Contingency planning
C)Contingency analysis
D)Buffering
Question
The estimation of activities' durations using some type of mathematical process is called:

A)mathematical estimating.
B)psychometric estimating.
C)econometric estimating.
D)parametric estimating.
Question
________ is an analysis used to evaluate the effects of variance on the schedule of project activities.

A)Schedule variance assessment
B)Performance measurement
C)Schedule variation control
D)Variance analysis
Question
________ is the process of estimating the duration of the project activities using both project scope and resource information.

A)Project duration estimation
B)Scope duration estimation
C)Resource estimation
D)Activity duration estimation
Question
Resource allocation:

A)plays a large role in determining activity duration.
B)is mostly an easy task.
C)is overrated.
D)does not affect activity duration.
Question
The longest path through a network diagram is the:

A)critical chain.
B)longest path.
C)network path.
D)critical path.
Question
The process of determining start and finish dates for project activities is called:

A)schedule development.
B)network diagramming.
C)start- finish analysis.
D)time management.
Question
________ is an estimating technique in which complex activities are further decomposed to a point where more accurate estimates can be made.

A)Expert judgment
B)Published estimating data
C)Alternatives analysis
D)Bottom- up estimating
Question
The use of mathematical techniques to shorten a project's duration is called:

A)schedule compression.
B)crashing.
C)PERT.
D)fast- tracking.
Question
The performance of activities in parallel that would normally be performed in sequence in an attempt to shorten the duration of a project is called:

A)crashing.
B)schedule compression.
C)fast- tracking.
D)PERT.
Question
________ is the measure of the alternative opportunities forgone in the choice of one good or activity over others.

A)Opportunity cost
B)Prospect cost
C)Forgone cost
D)Sunk cost
Question
The process of putting procedures and rules in place for controlling changes to the project schedules is called:

A)schedule management.
B)schedule procedure manual.
C)schedule model.
D)schedule control.
Question
________ slack is the time and activity can be delayed without affecting the overall completion date of a project.
Question
The prudent project manager should provide ________ rather than point estimates.
Question
Resource leveling heuristics are ________ used to allocate resources to project activities.

A)rules of thumb
B)policies
C)hard- and- fast rules
D)preferences
Question
________ are probabilistic analyses used to calculate the distribution of results.

A)Monaco simulations
B)Monte Carlo simulations
C)Bellagio simulations
D)Vegas simulations
Question
The selection of personnel may be influenced by the availability, costs, and ________ of the resource pool the project manager has access to.
Question
What are examples of resources?

A)Money, people, and materials
B)Technology and space
C)All of the above
D)None of the above
Question
The critical path method determines the sequence of task activities that directly affect the completion of a project by:

A)determining the longest path through a network diagram.
B)subtracting the shortest path from the longest path in a network diagram.
C)adding all activities in a network diagram.
D)determining the shortest path through a network diagram.
Question
A fundamental part of scheduling a project is to determine the tasks' durations, which involves ________ that need to be assigned to the tasks.
Question
The shortest time in which a project can be completed is shown by the:

A)shortest path.
B)longest path.
C)addition of all paths.
D)crucial path
Question
Critical chain scheduling:

A)does not use feeding buffers.
B)is not concerned with resources.
C)eliminates all buffers from the project.
D)eliminates any buffers from individual activities to create a project buffer.
Question
Human resources include:

A)support staff.
B)customers.
C)end users.
D)all of the above.
Question
The process of calculating expected, early, and late start and finish dates of a project is called:

A)schedule network analysis.
B)reserve analysis.
C)PERT analysis.
D)EEL analysis.
Question
The ________ is a very detailed listing of the resource requirements for the individual activities.

A)resource breakdown schedule
B)bill of resources
C)activity list
D)activity resource requirements
Question
The critical chain method is used when activities contend for ________ .
Question
Capital resources are the tools and ________ used to produce other goods and services.
Question
In terms of project time management, resource allocation plays a large role in determining ________
.
Question
The estimation of activities' durations by averaging optimistic, pessimistic, and most likely estimates is called:

A)OPL- method.
B)likelihood procedure.
C)three- point estimates.
D)duration averaging.
Question
The practice of dedicating extra resources to a particular activity in an attempt to finish the activity sooner than the scheduled completion date is called:

A)fast- tracking.
B)schedule compression.
C)crashing.
D)PERT.
Question
A(n) ________ is a hierarchical, graphical representation of all needed resources ordered by type or category.

A)activity resource requirements
B)bill of resources
C)resource graph
D)resource breakdown schedule
Question
Using critical chain scheduling, a ________ is added to any noncritical activity feeding into a critical activity.
Question
The ________ aids project managers in determining when activities can be performed given resources and constraints.
Question
The critical path is the ________ through a network diagram.
Question
The sequence of activities can be determined ________ the resources.
Question
________ is performing activities in parallel that would normally be performed in sequence to shorten the duration of a project.
Question
Critical chain scheduling uses a ________ to protect the final due date of a project.
Question
________ is the elapsed time between the start and the finish of an activity.
Question
________ is a process used to determine the magnitude and criticality of schedule variations.
Question
The resources used to complete tasks may also influence the ________ of project deliverables.
Question
________ is the process of determining start and finish dates for project activities.
Question
________ are dates that are imposed to meet some form of development deadline.
Question
Published estimating data is a form of ________ .
Question
An activity on the critical path is referred to as a ________ .
Question
The activity resource requirements should include any ________ made during the estimation process.
Question
For almost any activity, there is a tradeoff between the time needed, the resources invested, and the ________ of the final deliverable.
Question
The longest path through a network diagram illustrates the ________ in which a project can be completed.
Question
________ are probabilistic analyses used to calculate a distribution of likely results.
Question
The ________ determines the process for evaluating and implementing potential schedule changes.
Question
A ________ is a hierarchical graphical representation of all needed resources ordered by category.
Question
Free slack is also known as ________ .
Question
________ is an analysis to evaluate the effects of variance on the schedule of project activities.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/120
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 7: Managing Project Resources
1
Under conditions of unlimited resources the critical path:

A)and the critical chain are equal.
B)is shorter than the critical chain.
C)is longer than the critical chain.
D)is not affected by the critical chain.
A
2
Any activity on the critical path:

A)contains total slack.
B)is called critical activity.
C)is represented in blue in Microsoft Project.
D)contains free slack.
B
3
The elapsed time between start and finish of an activity is referred to as:

A)effort.
B)length.
C)duration.
D)time.
C
4
The process used to determine the magnitude and criticality of schedule variations is called:

A)criticality assessment.
B)order- of- magnitude estimation.
C)performance measurement.
D)critical path model.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
5
The time an activity can be delayed without affecting the immediately following activity is called:

A)lag time.
B)free slack.
C)lead time.
D)total slack.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
6
All of the following are techniques for estimating activity duration EXCEPT:

A)psychometric estimating.
B)expert judgment.
C)reserve analysis.
D)analogous estimating.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
7
The actual time spent working on an activity, not accounting for any breaks, is called:

A)length.
B)time.
C)effort.
D)duration.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
8
________ is any form of network analysis where resource management issues drive scheduling decisions.

A)Resource management
B)Schedule leveling
C)Resource analysis
D)Resource leveling
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
9
A ________ is a control system developed to outline the process for the evaluation and implementation of schedule changes.

A)schedule change control system
B)scope control system
C)project control system
D)schedule model control system
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
10
The ________ is a dedicated part of the organization whose purpose is to focus on various aspects of project management and provide services to the rest of the organization along those dimensions.

A)project management office
B)project support office
C)project maintenance office
D)project management bureau
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
11
A ________ contains data and information that are compiled and used in conjunction with manual methods or project management software to perform schedule network analysis and to generate the schedule.

A)project management plan
B)schedule repository
C)project workbook
D)schedule model
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
12
The estimation of activities' durations based upon the duration of similar activities is called:

A)similarity estimating.
B)psychometric estimating.
C)parametric estimating.
D)analogous estimating.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
13
Dates imposed to meet some type of development deadline are called:

A)external dependencies.
B)imposed dates.
C)mandatory dates.
D)none of the above.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
14
The critical path in a network diagram illustrates the:

A)effect of accumulated slack.
B)longest time in which a project is completed.
C)importance of resource leveling.
D)shortest time in which a project can be completed.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
15
Hard data from specific activities carried out on previous projects that may be used to more accurately estimate resource needs is called:

A)expert judgment.
B)bottom- up estimating.
C)alternatives analysis.
D)published estimating data.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
16
The estimation based on the experience of one or more experts on the particular activity or project is called:

A)published estimating data.
B)expert judgment.
C)bottom- up estimating.
D)alternatives analysis.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
17
The sequence of activities:

A)can be determined without considering resources.
B)cannot be determined without considering resources.
C)can only be determine when considering resources.
D)none of the above.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
18
In information systems development projects, ________ would be (an)example(s)of capital resources.

A)the project manager
B)both the development platform and the technical platform the software resides on
C)the development platform
D)the technological platform the software resides on
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
19
The time an activity can be delayed without affecting the overall completion date of a project is called:

A)lag time.
B)free slack.
C)total slack.
D)lead time.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
20
________ is an estimating technique in which trade- offs between the time needed, the resources invested, and the desired quality of the final deliverable are examined.

A)Alternatives analysis
B)Published estimating data
C)Expert judgment
D)Bottom- up estimating
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
21
Managing resources should be considered:

A)during execution of a project.
B)during all stages of a project.
C)during initiation and planning of a project.
D)during control and close- out stages of a project.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
22
The longest path through a network diagram, considering both task dependencies and resource dependencies is called:

A)critical path.
B)resource chain,
C)critical chain.
D)resource path.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
23
All of the following are tools and techniques to estimate resources EXCEPT:

A)expert judgment.
B)activity- resource analysis.
C)bottom- up estimating.
D)alternative analysis.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
24
Crashing and fast- tracking are ________ techniques.

A)schedule adjustment
B)schedule compression
C)path adjustment
D)schedule shortening
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
25
Inputs into the activity resource estimating process include:

A)process assets.
B)enterprise environmental factors.
C)outputs from prior stages of the project.
D)all of the above.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
26
________ is a technique that is used to estimate project duration when individual activity duration estimates are uncertain.

A)Likelihood procedure
B)Three- point estimate
C)OPR- method
D)PERT
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
27
________ use a process of evaluating alternative strategies by observing how changes to selected factors affect other factors and outcomes.

A)What- if analyses
B)Monaco analyses
C)If- then analyses
D)Monte Carlo analyses
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
28
Resources:

A)affect both the time and the cost of a project.
B)do not affect a project much.
C)affect the time to complete a project.
D)affect the cost of a project.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
29
________ is a technique used to establish contingency reserves during a project to guard against potential risks.

A)Reserve analysis
B)Contingency planning
C)Contingency analysis
D)Buffering
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
30
The estimation of activities' durations using some type of mathematical process is called:

A)mathematical estimating.
B)psychometric estimating.
C)econometric estimating.
D)parametric estimating.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
31
________ is an analysis used to evaluate the effects of variance on the schedule of project activities.

A)Schedule variance assessment
B)Performance measurement
C)Schedule variation control
D)Variance analysis
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
32
________ is the process of estimating the duration of the project activities using both project scope and resource information.

A)Project duration estimation
B)Scope duration estimation
C)Resource estimation
D)Activity duration estimation
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
33
Resource allocation:

A)plays a large role in determining activity duration.
B)is mostly an easy task.
C)is overrated.
D)does not affect activity duration.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
34
The longest path through a network diagram is the:

A)critical chain.
B)longest path.
C)network path.
D)critical path.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
35
The process of determining start and finish dates for project activities is called:

A)schedule development.
B)network diagramming.
C)start- finish analysis.
D)time management.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
36
________ is an estimating technique in which complex activities are further decomposed to a point where more accurate estimates can be made.

A)Expert judgment
B)Published estimating data
C)Alternatives analysis
D)Bottom- up estimating
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
37
The use of mathematical techniques to shorten a project's duration is called:

A)schedule compression.
B)crashing.
C)PERT.
D)fast- tracking.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
38
The performance of activities in parallel that would normally be performed in sequence in an attempt to shorten the duration of a project is called:

A)crashing.
B)schedule compression.
C)fast- tracking.
D)PERT.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
39
________ is the measure of the alternative opportunities forgone in the choice of one good or activity over others.

A)Opportunity cost
B)Prospect cost
C)Forgone cost
D)Sunk cost
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
40
The process of putting procedures and rules in place for controlling changes to the project schedules is called:

A)schedule management.
B)schedule procedure manual.
C)schedule model.
D)schedule control.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
41
________ slack is the time and activity can be delayed without affecting the overall completion date of a project.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
42
The prudent project manager should provide ________ rather than point estimates.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
43
Resource leveling heuristics are ________ used to allocate resources to project activities.

A)rules of thumb
B)policies
C)hard- and- fast rules
D)preferences
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
44
________ are probabilistic analyses used to calculate the distribution of results.

A)Monaco simulations
B)Monte Carlo simulations
C)Bellagio simulations
D)Vegas simulations
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
45
The selection of personnel may be influenced by the availability, costs, and ________ of the resource pool the project manager has access to.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
46
What are examples of resources?

A)Money, people, and materials
B)Technology and space
C)All of the above
D)None of the above
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
47
The critical path method determines the sequence of task activities that directly affect the completion of a project by:

A)determining the longest path through a network diagram.
B)subtracting the shortest path from the longest path in a network diagram.
C)adding all activities in a network diagram.
D)determining the shortest path through a network diagram.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
48
A fundamental part of scheduling a project is to determine the tasks' durations, which involves ________ that need to be assigned to the tasks.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
49
The shortest time in which a project can be completed is shown by the:

A)shortest path.
B)longest path.
C)addition of all paths.
D)crucial path
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
50
Critical chain scheduling:

A)does not use feeding buffers.
B)is not concerned with resources.
C)eliminates all buffers from the project.
D)eliminates any buffers from individual activities to create a project buffer.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
51
Human resources include:

A)support staff.
B)customers.
C)end users.
D)all of the above.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
52
The process of calculating expected, early, and late start and finish dates of a project is called:

A)schedule network analysis.
B)reserve analysis.
C)PERT analysis.
D)EEL analysis.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
53
The ________ is a very detailed listing of the resource requirements for the individual activities.

A)resource breakdown schedule
B)bill of resources
C)activity list
D)activity resource requirements
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
54
The critical chain method is used when activities contend for ________ .
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
55
Capital resources are the tools and ________ used to produce other goods and services.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
56
In terms of project time management, resource allocation plays a large role in determining ________
.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
57
The estimation of activities' durations by averaging optimistic, pessimistic, and most likely estimates is called:

A)OPL- method.
B)likelihood procedure.
C)three- point estimates.
D)duration averaging.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
58
The practice of dedicating extra resources to a particular activity in an attempt to finish the activity sooner than the scheduled completion date is called:

A)fast- tracking.
B)schedule compression.
C)crashing.
D)PERT.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
59
A(n) ________ is a hierarchical, graphical representation of all needed resources ordered by type or category.

A)activity resource requirements
B)bill of resources
C)resource graph
D)resource breakdown schedule
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
60
Using critical chain scheduling, a ________ is added to any noncritical activity feeding into a critical activity.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
61
The ________ aids project managers in determining when activities can be performed given resources and constraints.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
62
The critical path is the ________ through a network diagram.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
63
The sequence of activities can be determined ________ the resources.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
64
________ is performing activities in parallel that would normally be performed in sequence to shorten the duration of a project.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
65
Critical chain scheduling uses a ________ to protect the final due date of a project.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
66
________ is the elapsed time between the start and the finish of an activity.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
67
________ is a process used to determine the magnitude and criticality of schedule variations.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
68
The resources used to complete tasks may also influence the ________ of project deliverables.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
69
________ is the process of determining start and finish dates for project activities.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
70
________ are dates that are imposed to meet some form of development deadline.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
71
Published estimating data is a form of ________ .
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
72
An activity on the critical path is referred to as a ________ .
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
73
The activity resource requirements should include any ________ made during the estimation process.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
74
For almost any activity, there is a tradeoff between the time needed, the resources invested, and the ________ of the final deliverable.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
75
The longest path through a network diagram illustrates the ________ in which a project can be completed.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
76
________ are probabilistic analyses used to calculate a distribution of likely results.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
77
The ________ determines the process for evaluating and implementing potential schedule changes.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
78
A ________ is a hierarchical graphical representation of all needed resources ordered by category.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
79
Free slack is also known as ________ .
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
80
________ is an analysis to evaluate the effects of variance on the schedule of project activities.
Unlock Deck
Unlock for access to all 120 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 120 flashcards in this deck.