Deck 26: Cost Allocation and Activity-Based Costing
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/110
Play
Full screen (f)
Deck 26: Cost Allocation and Activity-Based Costing
1
The selection of the factory overhead allocation method is important because the method selected determines the accuracy of the product cost.
True
2
If the budgeted factory overhead cost is $460,000, the budgeted direct labor hours is 80,000, and the actual direct labor hours is 6,700 for the month, the amount of factory overhead to be allocated is $38,525 if the allocation is based on direct labor hours).
True
3
When a plantwide factory overhead rate is used, overhead costs are applied to all products by a single rate.
True
4
Multiple production department factory overhead rates are most useful when production departments significantly differ in their manufacturing processes.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
5
If the budgeted factory overhead cost is $460,000, the budgeted direct labor hours is 80,000, and the actual direct labor hours is 6,700 for the month, the factory overhead rate for the month is $68.65 if the allocation is based on direct labor hours).
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
6
Multiple production department factory overhead rates are less accurate than are plantwide factory overhead rates.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
7
Managers depend on product costing to make decisions regarding continuing operations and product mix.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
8
A single plantwide overhead rate method is very expensive to apply.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
9
Use of a plantwide factory overhead rate assumes that the activities causing overhead costs are different across different departments and products.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
10
A plantwide factory overhead rate is computed by dividing total budgeted factory overhead costs by the plantwide allocation base.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
11
Bob's Biscuit Corporation budgeted $1,200,000 of factory overhead cost for the coming year. Its plantwide allocation base, machine hours, is budgeted at 100,000 hours. Budgeted units to be produced are 200,000 units. Bob's plantwide factory overhead rate is $12.00 per machine hour.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
12
Multiple production department factory overhead rates are more accurate than are plantwide factory overhead rates.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
13
Managers depend on accurate factory overhead allocation to make decisions regarding product mix and product price.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
14
A plantwide factory overhead rate assumes that all overhead is directly related to one activity representing the entire plant.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
15
Zorn Co. budgeted $600,000 of factory overhead cost for the coming year. Its plantwide allocation base, machine hours, is budgeted at 100,000 hours. Budgeted units to be produced are 200,000 units. Zorn's plantwide factory overhead rate is $6.00 per unit.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
16
Multiple production department factory overhead rates are most useful when production departments are very similar in their manufacturing processes.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
17
Product costing consists of only direct materials and direct labor.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
18
If the activities causing overhead costs are different across different departments and products, use of a plantwide factory overhead rate will cause distorted product costs.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
19
When a plantwide factory overhead rate is used, the total overhead costs allocated to all products are the same.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
20
Use of a plantwide factory overhead rate assumes that the activities causing overhead costs are the same across all departments and products.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
21
Activity rates are computed by dividing the cost budgeted for each activity pool by the estimated activity base for that pool.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
22
Activity-based costing can only be used to allocate manufacturing factory overhead.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
23
In a service organization, the multiple department overhead rate method is the most effective in providing information about the cost of services.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
24
Which of the following does not rely on managerial decisions involving accurate product costing?
A) product constraints
B) emphasis of a product line
C) product mix
D) product price
A) product constraints
B) emphasis of a product line
C) product mix
D) product price
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
25
Estimated activity-base usage quantities are the total activity-base quantities related to each product.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
26
Activity-based costing can be used to allocate period costs to various products that the company sells.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
27
Service companies can effectively use activity-based costing to compute product service) costs.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
28
Activity-based costing is much easier to apply than single plantwide factory overhead allocation.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
29
Activity cost pools are assigned to products, using factory overhead rates for each activity.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
30
Activity cost pools are cost accumulations associated with a given activity.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
31
In an effort to simplify the multiple production department factory overhead rate method, the same rate can be used for all departments.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
32
ABC is used to allocate selling and administrative expenses to each product based on the product's individual differences in consuming these activities.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
33
Direct labor hours is not a cost pool that is regularly used in the activity-based costing method.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
34
Service companies can effectively use multiple department overhead rate costing to compute product service) costs.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
35
Use of a plantwide factory overhead rate distorts product costs when there are differences in the factory overhead rates across different production departments and when products require different ratios of allocation-base usage in each production department.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
36
Service companies can effectively use single facility-wide overhead costing to compute product service) costs.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
37
Service organizations can use activity-based costing to allocate selling and administrative costs to services provided.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
38
Use of a plantwide factory overhead rate does not distort product costs when there are differences in the factory overhead rates across different production departments.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
39
Use of a plantwide factory overhead rate does not distort product costs when products require different ratios of allocation-base usage in each production department.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
40
When production departments differ significantly in their manufacturing process, it is recommended that the single plantwide factory overhead rate be used for allocating factory overhead.
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
41
Using the single plantwide factory overhead rate with an allocation base of direct labor hours, how much factory overhead will Blackwelder Factory allocate to small lamp production if actual direct hours for the period is 285,000?
A) $275,000
B) $285,000
C) $440,000
D) $456,000
A) $275,000
B) $285,000
C) $440,000
D) $456,000
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
42
Which of the following is not a factory overhead allocation method?
A) single plantwide rate
B) multiple departmental rates
C) factory costing
D) activity-based costing
A) single plantwide rate
B) multiple departmental rates
C) factory costing
D) activity-based costing
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
43
The Ramapo Company produces two products, Blinks and Dinks. They are manufactured in two departments, Fabrication and Assembly. Data for the products and departments are listed below.
All of the machine hours take place in the Fabrication department, which has an estimated overhead of $84,000. All of the labor hours take place in the Assembly department, which has an estimated total overhead of $72,000.
The Ramapo Company uses a single overhead rate to apply all overhead costs based on labor hours. What is the overhead cost per unit for Dinks?
A) $77.00
B) $39.00
C) $19.50
D) $59.92

The Ramapo Company uses a single overhead rate to apply all overhead costs based on labor hours. What is the overhead cost per unit for Dinks?
A) $77.00
B) $39.00
C) $19.50
D) $59.92
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
44
Using the single plantwide factory overhead rate with an allocation base of direct labor hours, how much factory overhead will Blackwelder Factory allocate to desk lamp production if actual direct hours for the period is 118,000?
A) $118,000
B) $200,000
C) $188,800
D) $125,000
A) $118,000
B) $200,000
C) $188,800
D) $125,000
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
45
Adirondak Marketing Inc. manufactures two products, A and B. Presently; the company uses a single plantwide factory overhead rate for allocating overhead to products. However, management is considering moving to a multiple department rate system for allocating overhead. 
Calculate the overhead rate per unit for Product A in the painting department of Adirondack Marketing Inc.
A) $236.32 per unit
B) $325.00 per unit
C) $147.70 per unit
D) $161.00 per unit

Calculate the overhead rate per unit for Product A in the painting department of Adirondack Marketing Inc.
A) $236.32 per unit
B) $325.00 per unit
C) $147.70 per unit
D) $161.00 per unit
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
46
The Botosan Factory has determined that its budgeted factory overhead budget for the year is $13,500,000 and budgeted direct labor hours are 10,000,000. If the actual direct labor hours for the period are 350,000, how much overhead would be allocated to the period?
A) $675,000
B) $470,630
C) $472,500
D) $236,250
A) $675,000
B) $470,630
C) $472,500
D) $236,250
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
47
Blue Ridge Marketing Inc. manufactures two products, A and B. Presently; the company uses a single plantwide factory overhead rate for allocating overhead to products. However, management is considering moving to a multiple department rate system for allocating overhead. The following table presents information about estimated overhead and direct labor hours. 
Using a single plantwide rate, determine the overhead rate per unit for Blue Ridge Marketing Inc.'s Product B.
A) $496.00
B) $144.00
C) $640.00
D) $320.00

Using a single plantwide rate, determine the overhead rate per unit for Blue Ridge Marketing Inc.'s Product B.
A) $496.00
B) $144.00
C) $640.00
D) $320.00
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
48
Using the single plantwide factory overhead rate with an allocation base of direct labor hours, how much factory overhead will Challenger Factory allocate to regular widget production if budgeted production for the period is 75,000 units and actual production for the period is 72,000 units?
A) $168,750
B) $324,000
C) $162,000
D) $337,500
A) $168,750
B) $324,000
C) $162,000
D) $337,500
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
49
The Roget Factory has determined that its budgeted factory overhead budget for the year is $15,500,000. They plan to produce 2,000,000 units. Budgeted direct labor hours are 1,050,000 and budgeted machine hours are 750,000. Using the single plantwide factory overhead rate based on direct labor hours, calculate the factory overhead rate for the year.
A) $14.76
B) $20.67
C) $7.75
D) $77.50
A) $14.76
B) $20.67
C) $7.75
D) $77.50
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
50
Blue Ridge Marketing Inc. manufactures two products, A and B. Presently, the company uses a single plantwide factory overhead rate for allocating overhead to products. However, management is considering moving to a multiple department rate system for allocating overhead. The following table presents information about estimated overhead and direct labor hours. 
Determine the overhead rate in the Painting Department for each unit of Product B if Blue Ridge Marketing Inc. uses a multiple department rate system.
A) $49.60 per unit
B) $99.20 per unit
C) $28.80 per unit
D) $64.00 per unit

Determine the overhead rate in the Painting Department for each unit of Product B if Blue Ridge Marketing Inc. uses a multiple department rate system.
A) $49.60 per unit
B) $99.20 per unit
C) $28.80 per unit
D) $64.00 per unit
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
51
Using the single plantwide factory overhead rate with an allocation base of direct labor hours, how much factory overhead will Challenger Factory allocate to deluxe widget production if budgeted production for the period is 50,000 units and actual production for the period is 58,000 units?
A) $391,500
B) $225,000
C) $261,000
D) $337,500
A) $391,500
B) $225,000
C) $261,000
D) $337,500
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
52
Everest Co. uses a plantwide factory overhead rate based on direct labor hours. Overhead costs would be overcharged to which of the following departments?
A) A labor-intensive department
B) A capital-intensive department
C) A materials-intensive department
D) All of the above
A) A labor-intensive department
B) A capital-intensive department
C) A materials-intensive department
D) All of the above
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
53
Adirondak Marketing Inc. manufactures two products, A and B. Presently; the company uses a single plantwide factory overhead rate for allocating overhead to products. However, management is considering moving to a multiple department rate system for allocating overhead. 
Calculate the plantwide factory overhead rate for Adirondack Marketing Inc.
A) $25.00 per dlh
B) $0.07 per dlh
C) $14.77 per dlh
D) $ 6.25 per dlh

Calculate the plantwide factory overhead rate for Adirondack Marketing Inc.
A) $25.00 per dlh
B) $0.07 per dlh
C) $14.77 per dlh
D) $ 6.25 per dlh
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
54
The Ramapo Company produces two products, Blinks and Dinks. They are manufactured in two departments, Fabrication and Assembly. Data for the products and departments are listed below.
All of the machine hours take place in the Fabrication department, which has an estimated overhead of $84,000. All of the labor hours take place in the Assembly department, which has an estimated total overhead of $72,000.
The Ramapo Company uses a single overhead rate to apply all overhead costs based on labor hours. What is the overhead cost per unit for Blinks?
A) $78.00
B) $19.50
C) $37.45
D) $56.00

The Ramapo Company uses a single overhead rate to apply all overhead costs based on labor hours. What is the overhead cost per unit for Blinks?
A) $78.00
B) $19.50
C) $37.45
D) $56.00
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
55
Blue Ridge Marketing Inc. manufactures two products, A and B. Presently, the company uses a single plantwide factory overhead rate for allocating overhead to products. However, management is considering moving to a multiple department rate system for allocating overhead. The following table presents information about estimated overhead and direct labor hours. 
Determine the overhead from both production departments allocated to each unit of Product B if Blue Ridge Marketing Inc. uses a multiple department rate system.
A) $425.60 per unit
B) $115.20 per unit
C) $214.40 per unit
D) $320.00 per unit

Determine the overhead from both production departments allocated to each unit of Product B if Blue Ridge Marketing Inc. uses a multiple department rate system.
A) $425.60 per unit
B) $115.20 per unit
C) $214.40 per unit
D) $320.00 per unit
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
56
The Ramapo Company produces two products, Blinks and Dinks. They are manufactured in two departments, Fabrication and Assembly. Data for the products and departments are listed below.
All of the machine hours take place in the Fabrication department, which has an estimated overhead of $84,000. All of the labor hours take place in the Assembly department, which has an estimated total overhead of $72,000.
The Ramapo Company uses a single overhead rate to apply all overhead costs. What would the single plantwide rate be if it was based on machine hours instead of labor hours?
A) $9.00 per machine hour
B) $19.50 per machine hour
C) $7.43 per machine hour
D) $4.00 per machine hour

The Ramapo Company uses a single overhead rate to apply all overhead costs. What would the single plantwide rate be if it was based on machine hours instead of labor hours?
A) $9.00 per machine hour
B) $19.50 per machine hour
C) $7.43 per machine hour
D) $4.00 per machine hour
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
57
Pinacle Corp. budgeted $700,000 of overhead cost for the current year. Actual overhead costs for the year were $650,000. Pinacle's plantwide allocation base, machine hours, was budgeted at 100,000 hours. Actual machine hours were 80,000. A total of 100,000 units was budgeted to be produced and 98,000 units were actually produced. Pinacle's plantwide factory overhead rate for the current year is:
A) $8.13 per machine hour
B) $7.00 per machine hour
C) $6.50 per machine hour
D) $8.75 per machine hour
A) $8.13 per machine hour
B) $7.00 per machine hour
C) $6.50 per machine hour
D) $8.75 per machine hour
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
58
The Ramapo Company produces two products, Blinks and Dinks. They are manufactured in two departments, Fabrication and Assembly. Data for the products and departments are listed below.
All of the machine hours take place in the Fabrication department, which has an estimated overhead of $84,000. All of the labor hours take place in the Assembly department, which has an estimated total overhead of $72,000.
Common allocation bases are
A) direct labor dollars, direct labor hours, direct material dollars
B) direct labor dollars, direct labor hours, machine hours
C) direct labor dollars, direct labor hours, machine dollars
D) machine dollars, direct labor dollars, direct labor hours

Common allocation bases are
A) direct labor dollars, direct labor hours, direct material dollars
B) direct labor dollars, direct labor hours, machine hours
C) direct labor dollars, direct labor hours, machine dollars
D) machine dollars, direct labor dollars, direct labor hours
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
59
Blue Ridge Marketing Inc. manufactures two products, A and B. Presently, the company uses a single plantwide factory overhead rate for allocating overhead to products. However, management is considering moving to a multiple department rate system for allocating overhead. The following table presents information about estimated overhead and direct labor hours. 
Determine the overhead from both production departments allocated to each unit of Product A if Blue Ridge Marketing Inc. uses a multiple department rate system.
A) $396.80 per unit
B) $425.60 per unit
C) $320.00 per unit
D) $214.40 per unit

Determine the overhead from both production departments allocated to each unit of Product A if Blue Ridge Marketing Inc. uses a multiple department rate system.
A) $396.80 per unit
B) $425.60 per unit
C) $320.00 per unit
D) $214.40 per unit
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
60
Blue Ridge Marketing Inc. manufactures two products, A and B. Presently, the company uses a single plantwide factory overhead rate for allocating overhead to products. However, management is considering moving to a multiple department rate system for allocating overhead. The following table presents information about estimated overhead and direct labor hours. 
Determine the overhead rate in the Finishing Department for each unit of Product A if Blue Ridge Marketing Inc. uses a multiple department rate system.
A) $99.20 per unit
B) $49.60 per unit
C) $64.00 per unit
D) $28.80 per unit

Determine the overhead rate in the Finishing Department for each unit of Product A if Blue Ridge Marketing Inc. uses a multiple department rate system.
A) $99.20 per unit
B) $49.60 per unit
C) $64.00 per unit
D) $28.80 per unit
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
61
The Aleutian Company produces two products, Rings and Dings. They are manufactured in two departments-Fabrication and Assembly. Data for the products and departments are listed below. All of the machine hours take place in the Fabrication Department, which has an estimated overhead of $90,000. All of the labor hours take place in the Assembly Department, which has an estimated total overhead of $105,000.
The Aleutian Company uses departmental overhead rates. The Fabrication Department uses machine hours for an allocation base, and the Assembly Department uses labor hours.
-What is the overhead cost per unit for Dings?
A) $65.25
B) $56.75
C) $23.25
D) $64.50
The Aleutian Company uses departmental overhead rates. The Fabrication Department uses machine hours for an allocation base, and the Assembly Department uses labor hours.
-What is the overhead cost per unit for Dings?
A) $65.25
B) $56.75
C) $23.25
D) $64.50
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
62
Which of the following are the two most common allocation bases for factory overhead?
A) Total overhead dollars and machine hours
B) Direct labor hours and machine hours
C) Direct labor hours and factory expenses
D) Machine hours and factory expenses
A) Total overhead dollars and machine hours
B) Direct labor hours and machine hours
C) Direct labor hours and factory expenses
D) Machine hours and factory expenses
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
63
If the budget estimates that a desk lamp will require 1 hours of finishing and 2 hours of production, what is the total amount of factory overhead the Kaumajet Factory will allocate to desk lamps using the multiple production department factory overhead rate method with an allocation base of direct labor hours, if 26,000 units are produced?
A) $540,000
B) $187,200
C) $475,000
D) $288,600
A) $540,000
B) $187,200
C) $475,000
D) $288,600
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
64
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below.

-Determine the activity-based cost for each wire drive unit.
A) $204.13
B) $173.51
C) $744.06
D) $394.12

-Determine the activity-based cost for each wire drive unit.
A) $204.13
B) $173.51
C) $744.06
D) $394.12
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
65
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below.

-Determine the activity rate for production per machine hour.
A) $62.50
B) $150.00
C) $75.00
D) $176.47

-Determine the activity rate for production per machine hour.
A) $62.50
B) $150.00
C) $75.00
D) $176.47
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
66
Using multiple department factory overhead rates instead of a single plantwide factory overhead rate:
A) results in more accurate product costs
B) results in distorted product costs
C) is simpler and less expensive to compute than a plantwide rate
D) applies overhead costs to all departments equally
A) results in more accurate product costs
B) results in distorted product costs
C) is simpler and less expensive to compute than a plantwide rate
D) applies overhead costs to all departments equally
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
67
The Aleutian Company produces two products, Rings and Dings. They are manufactured in two departments-Fabrication and Assembly. Data for the products and departments are listed below. All of the machine hours take place in the Fabrication Department, which has an estimated overhead of $90,000. All of the labor hours take place in the Assembly Department, which has an estimated total overhead of $105,000.
The Aleutian Company uses departmental overhead rates. The Fabrication Department uses machine hours for an allocation base, and the Assembly Department uses labor hours.
-What is the Assembly Department overhead rate per labor hour?
A) $10.50
B) $19.50
C) $3.75
D) $4.38
The Aleutian Company uses departmental overhead rates. The Fabrication Department uses machine hours for an allocation base, and the Assembly Department uses labor hours.
-What is the Assembly Department overhead rate per labor hour?
A) $10.50
B) $19.50
C) $3.75
D) $4.38
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
68
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below.

-Determine the activity-based cost for each disk drive unit.
A) $92.25
B) $130.69
C) $394.12
D) $279.57

-Determine the activity-based cost for each disk drive unit.
A) $92.25
B) $130.69
C) $394.12
D) $279.57
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
69
If the budget estimates that a desk lamp will require 1 hours of finishing and 2 hours of production, how much factory overhead will the Kaumajet Factory allocate to each unit of desk lamps using the multiple production department factory overhead rate method with an allocation base of direct labor hours?
A) $11.10
B) $4.91
C) $5.00
D) $7.20
A) $11.10
B) $4.91
C) $5.00
D) $7.20
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
70
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below.

-Determine the activity rate for materials handling per move.
A) $58.82
B) $50.00
C) $20.83
D) $80.65

-Determine the activity rate for materials handling per move.
A) $58.82
B) $50.00
C) $20.83
D) $80.65
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
71
If the budget estimates that a table lamp will require 2 hours of finishing and 1 hours of production, what is the total amount of factory overhead the Kaumajet Factory will allocate to table lamps using the multiple production department factory overhead rate method with an allocation base of direct labor hours, if 75,000 units are produced?
A) $368,250
B) $540,000
C) $832,500
D) $475,000
A) $368,250
B) $540,000
C) $832,500
D) $475,000
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
72
The Aleutian Company produces two products, Rings and Dings. They are manufactured in two departments-Fabrication and Assembly. Data for the products and departments are listed below. All of the machine hours take place in the Fabrication Department, which has an estimated overhead of $90,000. All of the labor hours take place in the Assembly Department, which has an estimated total overhead of $105,000.
The Aleutian Company uses departmental overhead rates. The Fabrication Department uses machine hours for an allocation base, and the Assembly Department uses labor hours.
-What is the overhead cost per unit for Rings?
A) $65.25
B) $23.25
C) $44.10
D) $64.50
The Aleutian Company uses departmental overhead rates. The Fabrication Department uses machine hours for an allocation base, and the Assembly Department uses labor hours.
-What is the overhead cost per unit for Rings?
A) $65.25
B) $23.25
C) $44.10
D) $64.50
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
73
Using a plantwide factory overhead rate distorts product costs when:
A) products require different ratios of allocation-base usage in each production department
B) significant differences exist in the factory overhead rates used across different production departments
C) both A and B are true
D) neither A nor B are true
A) products require different ratios of allocation-base usage in each production department
B) significant differences exist in the factory overhead rates used across different production departments
C) both A and B are true
D) neither A nor B are true
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
74
Blue Ridge Marketing Inc. manufactures two products, A and B. Presently, the company uses a single plantwide factory overhead rate for allocating overhead to products. However, management is considering moving to a multiple department rate system for allocating overhead. The following table presents information about estimated overhead and direct labor hours. 
If the budget estimates that a table lamp will require 2 hours of finishing and 1 hours of production, how much factory overhead will the Kaumajet Factory allocate to each unit of table lamp using the multiple production department factory overhead rate method with an allocation base of direct labor hours?
A) $6.33
B) $4.91
C) $5.00
D) $7.20

If the budget estimates that a table lamp will require 2 hours of finishing and 1 hours of production, how much factory overhead will the Kaumajet Factory allocate to each unit of table lamp using the multiple production department factory overhead rate method with an allocation base of direct labor hours?
A) $6.33
B) $4.91
C) $5.00
D) $7.20
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
75
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below.

-Determine the activity rate for product development per change.
A) $73,000
B) $8,588
C) $30,417
D) $16,222

-Determine the activity rate for product development per change.
A) $73,000
B) $8,588
C) $30,417
D) $16,222
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
76
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below.

-Determine the activity rate for procurement per purchase order.
A) $43.53
B) $18.50
C) $15.42
D) $37.00

-Determine the activity rate for procurement per purchase order.
A) $43.53
B) $18.50
C) $15.42
D) $37.00
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
77
Scoresby Co. uses 6 machine hours and 2 direct labor hours to produce Product X. It uses 8 machine hours and 16 direct labor hours to produce Product Y. Scoresby's Assembly and Finishing departments have factory overhead rates of $240 per machine hour and $160 per direct labor hour, respectively. How much overhead cost will be charged to the two products?
A) Product X = $3,200; Product Y = $9,600
B) Product X = $800; Product Y = $800
C) Product X = $1,760; Product Y = $4,480
D) Product X = $1,440; Product Y = $2,560
A) Product X = $3,200; Product Y = $9,600
B) Product X = $800; Product Y = $800
C) Product X = $1,760; Product Y = $4,480
D) Product X = $1,440; Product Y = $2,560
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
78
All of the following can be used as an allocation base for calculating factory overhead rates except:
A) direct labor dollars
B) direct labor hours
C) machine hours
D) total units produced
A) direct labor dollars
B) direct labor hours
C) machine hours
D) total units produced
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
79
The Aleutian Company produces two products, Rings and Dings. They are manufactured in two departments-Fabrication and Assembly. Data for the products and departments are listed below. All of the machine hours take place in the Fabrication Department, which has an estimated overhead of $90,000. All of the labor hours take place in the Assembly Department, which has an estimated total overhead of $105,000.
The Aleutian Company uses departmental overhead rates. The Fabrication Department uses machine hours for an allocation base, and the Assembly Department uses labor hours.
-What is the Fabrication Department overhead rate per machine hour?
A) $10.50
B) $9.00
C) $8.12
D) $3.75
The Aleutian Company uses departmental overhead rates. The Fabrication Department uses machine hours for an allocation base, and the Assembly Department uses labor hours.
-What is the Fabrication Department overhead rate per machine hour?
A) $10.50
B) $9.00
C) $8.12
D) $3.75
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck
80
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below.

-Determine the activity rate per production order for scheduling.
A) $200.00
B) $20.00
C) $29.41
D) $10.42

-Determine the activity rate per production order for scheduling.
A) $200.00
B) $20.00
C) $29.41
D) $10.42
Unlock Deck
Unlock for access to all 110 flashcards in this deck.
Unlock Deck
k this deck