Deck 4: Projects

Full screen (f)
exit full mode
Question
Complex projects are often subdivided into a series of tasks that are typically configured to be not longer than several months in duration.
Use Space or
up arrow
down arrow
to flip the card.
Question
CPM is an abbreviation for critical path method.
Question
The Gantt chart is an example of a project control chart.
Question
The second step in managing a project is writing the statement of work.
Question
A disadvantage of a matrix project organizational structure is that a project manager is held responsible for successful completion of the project.
Question
Slack activity time is the difference between the early start and the late finish of a project activity time.
Question
One of the advantages of a functional project organizational structure is that a team member can work on several projects.
Question
A project may be defined as a series of related jobs directed toward some major output and requiring a significant period of time to perform.
Question
Upper-level management must decide between pure, functional, and matrix structures as ways to organize projects.
Question
In a CPM analysis, if you subtract the early start from the late start, the result is the activity's slack time.
Question
The fact that organizations are flattening is one of the reasons that project management is important.
Question
An event unit package is a subdivision of a project.
Question
A matrix project attempts to blend properties of functional and pure project structures.
Question
The critical path in a CPM analysis is always the shortest path through the network.
Question
A work breakdown structure is used in project management but it is not used when the critical path method is involved.
Question
In CPM, the late start time estimate is the latest time you can start an activity and still keep the entire project on schedule.
Question
In a CPM analysis, if you subtract the late finish from the early finish, the result is the activity's slack time.
Question
The critical path in a project is that sequence of activities that consume the longest amount of time in a project network of activities.
Question
One of the disadvantages of a pure project organizational structure is that the project manager has full authority over the project.
Question
The critical path of activities in a project is the sequence of activities that form the shortest chain in a project network of activities.
Question
The activity direct costs associated with a project might include giving workers overtime to complete a project in less than the expected time.
Question
Derivative projects have high levels of change.
Question
Earned value management (EVM) is a technique for measuring project progress in an objective manner.
Question
One of the assumptions made using CPM is that project activities can be identified with clear beginning and ending points.
Question
Breakthrough projects are those that provide fundamental improvements to existing products.
Question
Derivative projects are those that address incremental changes to products or processes.
Question
Functional projects have high levels of team member motivation.
Question
You are managing a project and need to cut the cost of the project. You decide to transfer workers to another job to cut the project's costs. Costs associated with transferring the workers are an example of project indirect costs.
Question
The project indirect costs associated with a project include overhead, facilities, and resource opportunity costs.
Question
Calculating the early start and early finish times for each activity in a CPM analysis does not provide any useful information.
Question
In the time-cost CPM model, cost is assumed to be a linear function of time.
Question
With a pure project, team members report to multiple managers.
Question
One of the assumptions made using CPM is that project activity sequence relationships can be specified and networked.
Question
Earned value management (EVM) has the capability to combine measurements of scope, schedule, and cost in a project.
Question
The critical path in a CPM analysis is found by locating the activities times with zero slack.
Question
The valuations in an earned value management analysis must be either profits or revenue.
Question
Pure projects suffer from duplication of resources.
Question
A project milestone is a specific event to be reached by a particular point in time.
Question
Using the time-cost CPM model, the crash time is the shortest possible time allowed for each activity in the project.
Question
When reducing the planned duration of a project using the time-cost CPM model, we select the activity to crash by determining the cost of each alternative and selecting the one whose cost is the greatest.
Question
Which of the following is a graphic project report used in project management?

A) Project proposal
B) Approved project plan
C) Humphrey chart
D) Equipment and supplies chart
E) Cost and performance tracking schedule
Question
A project can be subdivided into which of the following?

A) Job orders
B) Sub-jobs
C) Work packages
D) Sub-paths
E) Events and decisions
Question
Some of the advantages of a functional project where the project is housed in a functional division include which of the following?

A) The project manager has full authority over the project.
B) Team pride, motivation, and commitment are high.
C) A team member can work on several projects.
D) Needs of the client are secondary.
E) None of these choices are correct
Question
A simple project listing of five activities and their respective time estimates are presented here: <strong>A simple project listing of five activities and their respective time estimates are presented here:   Using CPM, which activities make up the critical path?</strong> A) A, C, D, E B) A, B, D, E C) A, C, B, D, E D) A, D, E E) None of these choices are correct <div style=padding-top: 35px> Using CPM, which activities make up the critical path?

A) A, C, D, E
B) A, B, D, E
C) A, C, B, D, E
D) A, D, E
E) None of these choices are correct
Question
An advantage of a pure project where self-contained teams work full time on a project is which of the following?

A) Team members can work on several projects.
B) Functional area is a "home" after the project is completed.
C) There are duplicated resources.
D) Lines of communication are shortened.
E) Overall organizational policies and goals can be ignored.
Question
In a Gantt chart, the horizontal axis is usually which of the following?

A) Activities
B) Cost
C) Profit
D) Time
E) Milestones
Question
What is a work breakdown structure?

A) A list of the activities making up the higher levels of the project
B) A definition of the hierarchy of project tasks, subtasks, and work packages
C) A depiction of the activities making up a project
D) A Gantt chart
E) A structure that is incompatible with the critical path method
Question
A series of projects that are organized in such a way that each project utilizes people from different functional areas is using which of the following organizational structures?

A) Matrix project
B) Integrated task force
C) Functional project
D) Pure project
E) Cross-functional flexible team
Question
You have been placed in charge of a large project. Shortened communication lines are required to ensure quick resolution of problems as they arise. You recognize that the project is going to take a lot of time and require a lot of team pride, motivation, and commitment by all members. Which project management structure should you use in this situation?

A) Pure project
B) Task force
C) Matrix project
D) Functional project
E) PERT
Question
PERT is an abbreviation for which of the following methodologies?

A) Product evaluation, result, and treatment
B) Programming and evaluation realization technology
C) Program evaluation and review technique
D) Process evaluation and review technology
E) It is a name, not an abbreviation for anything.
Question
A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here: <strong>A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here: <sub> </sub>   Using CPM, what is the latest finish time for the last activity in this project (i.e., the total time to complete the project)?</strong> A) 9 days B) 10 days C) 11 days D) 12 days E) 13 days <div style=padding-top: 35px> Using CPM, what is the latest finish time for the last activity in this project (i.e., the total time to complete the project)?

A) 9 days
B) 10 days
C) 11 days
D) 12 days
E) 13 days
Question
You have just been assigned to oversee a series of projects. Functional areas will loan you personnel for each project, and separate project managers will be responsible for separate projects. These project managers will report to you. Which project management structure is being used?

A) Pure project
B) Task force
C) Matrix project
D) Functional project
E) PERT
Question
A simple project listing of five activities, their predecessors, and their respective time estimates are presented here: <strong>A simple project listing of five activities, their predecessors, and their respective time estimates are presented here:   Using CPM, what is the latest finish time for the last activity in this project (i.e., the total time to complete the project)?</strong> A) 10 days B) 7 days C) 8 days D) 12 days E) 9 days <div style=padding-top: 35px> Using CPM, what is the latest finish time for the last activity in this project (i.e., the total time to complete the project)?

A) 10 days
B) 7 days
C) 8 days
D) 12 days
E) 9 days
Question
A tracking Gantt chart superimposes the current schedule onto a baseline plan so deviations are easily noticed.
Question
If a single estimate of the time required to complete an activity is not reliable, the best procedure is to use a mean and standard deviation (or variance) for each activity.
Question
A simple project listing of five activities, their predecessors, and their respective time estimates are presented here: <strong>A simple project listing of five activities, their predecessors, and their respective time estimates are presented here:   Using the CPM, which activities have slack in this project?</strong> A) A B) B C) C D) D E) C and E <div style=padding-top: 35px> Using the CPM, which activities have slack in this project?

A) A
B) B
C) C
D) D
E) C and E
Question
A project starts out as which of the following?

A) A statement of work
B) Critical path method (CPM)
C) A series of milestones
D) A Gantt chart
E) A latest-start-time estimate
Question
Currently, there are only two major companies producing project management software, Microsoft, with Microsoft Project, and Primavera, with Primavera Project Planner.
Question
A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here: <strong>A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here:<sub> </sub>   Using CPM, which activities make up the critical path?</strong> A) A, B, D, F, G B) A, C, E, F, G C) A, C, B, F, E D) A, D, E E) None of these choices are correct <div style=padding-top: 35px> Using CPM, which activities make up the critical path?

A) A, B, D, F, G
B) A, C, E, F, G
C) A, C, B, F, E
D) A, D, E
E) None of these choices are correct
Question
You are looking at a chart that has the terms BCWS, BCWP, and AC indicating lines on the chart. What kind of chart are you looking at?

A) Gantt chart
B) PERT chart
C) Bar/milestone chart
D) Total program cost breakdown
E) EVM chart
Question
For an activity in a CPM analysis, the early finish time is 20 and the late finish time is 20. Which of the following statements is true?

A) The activity's late start must happen before its early start.
B) The activity is on the critical path.
C) The slack for this activity is 20.
D) The duration of this task is zero.
E) The duration of this task is 20.
Question
Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs. <strong>Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs. <sub> </sub>   What are the total time of this project and total normal cost?</strong> A) Total time is 13 days, total cost is $1,200. B) Total time is 12 days, total cost is $1,700. C) Total time is 11 days, total cost is $1,600. D) Total time is 10 days, total cost is $1,750. E) Total time is 9 days, total cost is $1,700. <div style=padding-top: 35px> What are the total time of this project and total normal cost?

A) Total time is 13 days, total cost is $1,200.
B) Total time is 12 days, total cost is $1,700.
C) Total time is 11 days, total cost is $1,600.
D) Total time is 10 days, total cost is $1,750.
E) Total time is 9 days, total cost is $1,700.
Question
You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project "direct costs" are given here. <strong>You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project direct costs are given here. <sub> </sub>   The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100. If you crash this project by one day,What is the total (i.e., direct and indirect) project cost?</strong> A) $2,150 B) $2,300 C) $2,400 D) $2,450 E) $2,500 <div style=padding-top: 35px> The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100. If you crash this project by one day,What is the total (i.e., direct and indirect) project cost?

A) $2,150
B) $2,300
C) $2,400
D) $2,450
E) $2,500
Question
A structure for organizing a project where a self-contained team works full time on the project is:

A) pure project
B) modified project
C) functional project
D) hybrid project
E) matrix project
Question
Popular project management software used in mid-sized projects is

A) Microsoft Word.
B) Microsoft Primavera.
C) Microsoft Project.
D) Microsoft Excel.
E) None of thesechoices are correct
Question
You have the following time and cost information for use in a time-cost CPM scheduling model. <strong>You have the following time and cost information for use in a time-cost CPM scheduling model.   What are the three costs per unit of time to expedite each activity?</strong> A) A = $300, B = $200, C = $300 B) A = $100, B = $200, C = $400 C) A = $200, B = $200, C = $200 D) A = $100, B = $400, C = $300 E) A = $200, B = $300, C = $400 <div style=padding-top: 35px> What are the three costs per unit of time to expedite each activity?

A) A = $300, B = $200, C = $300
B) A = $100, B = $200, C = $400
C) A = $200, B = $200, C = $200
D) A = $100, B = $400, C = $300
E) A = $200, B = $300, C = $400
Question
In this structure, each project uses people from different functional areas. A dedicated project manager decides what tasks need to be performed and when, but the functional managers control which people to use.

A) Pure project
B) Modified project
C) Functional project
D) Hybrid project
E) Matrix project
Question
For an activity in a CPM analysis, the early start time is 8 and the late start time is 10. Which of the following statements is true?

A) The late finish is 12.
B) The early finish is 10.
C) The slack for this activity is 2.
D) The duration of this activity is 2.
E) The activity is on the critical path.
Question
A listing of immediate predecessor activities is important information in a CPM analysis for which of the following reasons?

A) It specifies the relationships in the CPM network of activities.
B) It provides useful timing information.
C) It includes cost information.
D) It is the probability information required in the final step of CPM.
E) None of these choices are correct
Question
In this structure, team members are assigned from the functional units of the organization. The team members remain a part of their functional units and typically are not dedicated to the project.

A) Pure project
B) Modified project
C) Functional project
D) Hybrid project
E) Matrix project
Question
You know when you have arrived at the optimal solution in using the time-cost CPM scheduling model analysis when what happens?

A) You have found the critical path.
B) You have run out of crash time.
C) You no longer have a linear relationship with costs.
D) You have reached the minimum total cost.
E) You have run out of crash costs.
Question
In CPM analysis, it is generally expected that the relationship between activity direct costs and project indirect costs will be which of the following?

A) Positively related
B) Optimally related
C) Negatively related
D) Not related
E) Fractionally related
Question
You have just used the network planning model and found the critical path length is 60 days and there are two critical paths. The standard deviation of the first critical path is 10 days and the s.d. of the second critical path is 15 days. The probability that the project will be completed in 70 days or less is equal to (2 decimal accuracy).

A) 0.84
B) 0.25
C) 0.16
D) 0.75
E) 0.66
Question
A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here: <strong>A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here:<sub> </sub>   Using CPM, which activities have slack in this project?</strong> A) A, B, C B) B, D C) Only C D) C, E E) F, G <div style=padding-top: 35px> Using CPM, which activities have slack in this project?

A) A, B, C
B) B, D
C) Only C
D) C, E
E) F, G
Question
You have just performed a CPM analysis and have found that more than one path through the project network has zero slack values. What can you conclude?

A) You have incorrectly performed the analysis.
B) You have multiple critical paths.
C) Only one path is optimal.
D) More than one path is optimal.
E) The project will not be completed by the desired time.
Question
You have just used the network planning model and found the critical path length is 30 days and the variance of the critical path is 25 days. The probability that the project will be completed in 33 days or less is equal to (2 decimal accuracy).

A) 0.73
B) 0.55
C) 0.12
D) 0.27
E) 0.60
Question
You have just used the network planning model for a county road resurfacing project and found the critical path length is 40 days and the standard deviation of the critical path is 10 days. Suppose you want to pick a time (in days) within which you will complete the project with 90% confidence level. What should be that time (in days and round to the nearest whole number)?

A) 40
B) 13
C) 37
D) 29
E) 53
Question
Which of the following is not an advantage of a pure project?

A) The project manager has full authority over the project.
B) Team members report to one boss.
C) A team member can work on several projects.
D) Decisions are made quickly.
E) Team motivation is high.
Question
You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project "direct costs" are given here. <strong>You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project direct costs are given here. <sub> </sub>   The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100. At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs)?</strong> A) 16 days B) 15 days C) 14 days D) 13 days E) 12 days <div style=padding-top: 35px> The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100.
At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs)?

A) 16 days
B) 15 days
C) 14 days
D) 13 days
E) 12 days
Question
Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs. <strong>Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs. <sub> </sub>   If you crash this project to reduce the total time by one day, what is the total time of the project and total cost?</strong> A) Total time is 13 days, total cost is $1,500. B) Total time is 12 days, total cost is $2,000. C) Total time is 12 days, total cost is $2,300. D) Total time is 11 days, total cost is $1,850. E) Total time is 11 days, total cost is $2,350. <div style=padding-top: 35px> If you crash this project to reduce the total time by one day, what is the total time of the project and total cost?

A) Total time is 13 days, total cost is $1,500.
B) Total time is 12 days, total cost is $2,000.
C) Total time is 12 days, total cost is $2,300.
D) Total time is 11 days, total cost is $1,850.
E) Total time is 11 days, total cost is $2,350.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/108
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 4: Projects
1
Complex projects are often subdivided into a series of tasks that are typically configured to be not longer than several months in duration.
True
2
CPM is an abbreviation for critical path method.
True
3
The Gantt chart is an example of a project control chart.
True
4
The second step in managing a project is writing the statement of work.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
5
A disadvantage of a matrix project organizational structure is that a project manager is held responsible for successful completion of the project.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
6
Slack activity time is the difference between the early start and the late finish of a project activity time.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
7
One of the advantages of a functional project organizational structure is that a team member can work on several projects.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
8
A project may be defined as a series of related jobs directed toward some major output and requiring a significant period of time to perform.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
9
Upper-level management must decide between pure, functional, and matrix structures as ways to organize projects.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
10
In a CPM analysis, if you subtract the early start from the late start, the result is the activity's slack time.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
11
The fact that organizations are flattening is one of the reasons that project management is important.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
12
An event unit package is a subdivision of a project.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
13
A matrix project attempts to blend properties of functional and pure project structures.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
14
The critical path in a CPM analysis is always the shortest path through the network.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
15
A work breakdown structure is used in project management but it is not used when the critical path method is involved.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
16
In CPM, the late start time estimate is the latest time you can start an activity and still keep the entire project on schedule.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
17
In a CPM analysis, if you subtract the late finish from the early finish, the result is the activity's slack time.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
18
The critical path in a project is that sequence of activities that consume the longest amount of time in a project network of activities.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
19
One of the disadvantages of a pure project organizational structure is that the project manager has full authority over the project.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
20
The critical path of activities in a project is the sequence of activities that form the shortest chain in a project network of activities.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
21
The activity direct costs associated with a project might include giving workers overtime to complete a project in less than the expected time.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
22
Derivative projects have high levels of change.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
23
Earned value management (EVM) is a technique for measuring project progress in an objective manner.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
24
One of the assumptions made using CPM is that project activities can be identified with clear beginning and ending points.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
25
Breakthrough projects are those that provide fundamental improvements to existing products.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
26
Derivative projects are those that address incremental changes to products or processes.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
27
Functional projects have high levels of team member motivation.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
28
You are managing a project and need to cut the cost of the project. You decide to transfer workers to another job to cut the project's costs. Costs associated with transferring the workers are an example of project indirect costs.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
29
The project indirect costs associated with a project include overhead, facilities, and resource opportunity costs.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
30
Calculating the early start and early finish times for each activity in a CPM analysis does not provide any useful information.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
31
In the time-cost CPM model, cost is assumed to be a linear function of time.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
32
With a pure project, team members report to multiple managers.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
33
One of the assumptions made using CPM is that project activity sequence relationships can be specified and networked.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
34
Earned value management (EVM) has the capability to combine measurements of scope, schedule, and cost in a project.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
35
The critical path in a CPM analysis is found by locating the activities times with zero slack.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
36
The valuations in an earned value management analysis must be either profits or revenue.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
37
Pure projects suffer from duplication of resources.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
38
A project milestone is a specific event to be reached by a particular point in time.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
39
Using the time-cost CPM model, the crash time is the shortest possible time allowed for each activity in the project.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
40
When reducing the planned duration of a project using the time-cost CPM model, we select the activity to crash by determining the cost of each alternative and selecting the one whose cost is the greatest.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
41
Which of the following is a graphic project report used in project management?

A) Project proposal
B) Approved project plan
C) Humphrey chart
D) Equipment and supplies chart
E) Cost and performance tracking schedule
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
42
A project can be subdivided into which of the following?

A) Job orders
B) Sub-jobs
C) Work packages
D) Sub-paths
E) Events and decisions
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
43
Some of the advantages of a functional project where the project is housed in a functional division include which of the following?

A) The project manager has full authority over the project.
B) Team pride, motivation, and commitment are high.
C) A team member can work on several projects.
D) Needs of the client are secondary.
E) None of these choices are correct
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
44
A simple project listing of five activities and their respective time estimates are presented here: <strong>A simple project listing of five activities and their respective time estimates are presented here:   Using CPM, which activities make up the critical path?</strong> A) A, C, D, E B) A, B, D, E C) A, C, B, D, E D) A, D, E E) None of these choices are correct Using CPM, which activities make up the critical path?

A) A, C, D, E
B) A, B, D, E
C) A, C, B, D, E
D) A, D, E
E) None of these choices are correct
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
45
An advantage of a pure project where self-contained teams work full time on a project is which of the following?

A) Team members can work on several projects.
B) Functional area is a "home" after the project is completed.
C) There are duplicated resources.
D) Lines of communication are shortened.
E) Overall organizational policies and goals can be ignored.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
46
In a Gantt chart, the horizontal axis is usually which of the following?

A) Activities
B) Cost
C) Profit
D) Time
E) Milestones
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
47
What is a work breakdown structure?

A) A list of the activities making up the higher levels of the project
B) A definition of the hierarchy of project tasks, subtasks, and work packages
C) A depiction of the activities making up a project
D) A Gantt chart
E) A structure that is incompatible with the critical path method
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
48
A series of projects that are organized in such a way that each project utilizes people from different functional areas is using which of the following organizational structures?

A) Matrix project
B) Integrated task force
C) Functional project
D) Pure project
E) Cross-functional flexible team
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
49
You have been placed in charge of a large project. Shortened communication lines are required to ensure quick resolution of problems as they arise. You recognize that the project is going to take a lot of time and require a lot of team pride, motivation, and commitment by all members. Which project management structure should you use in this situation?

A) Pure project
B) Task force
C) Matrix project
D) Functional project
E) PERT
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
50
PERT is an abbreviation for which of the following methodologies?

A) Product evaluation, result, and treatment
B) Programming and evaluation realization technology
C) Program evaluation and review technique
D) Process evaluation and review technology
E) It is a name, not an abbreviation for anything.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
51
A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here: <strong>A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here: <sub> </sub>   Using CPM, what is the latest finish time for the last activity in this project (i.e., the total time to complete the project)?</strong> A) 9 days B) 10 days C) 11 days D) 12 days E) 13 days Using CPM, what is the latest finish time for the last activity in this project (i.e., the total time to complete the project)?

A) 9 days
B) 10 days
C) 11 days
D) 12 days
E) 13 days
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
52
You have just been assigned to oversee a series of projects. Functional areas will loan you personnel for each project, and separate project managers will be responsible for separate projects. These project managers will report to you. Which project management structure is being used?

A) Pure project
B) Task force
C) Matrix project
D) Functional project
E) PERT
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
53
A simple project listing of five activities, their predecessors, and their respective time estimates are presented here: <strong>A simple project listing of five activities, their predecessors, and their respective time estimates are presented here:   Using CPM, what is the latest finish time for the last activity in this project (i.e., the total time to complete the project)?</strong> A) 10 days B) 7 days C) 8 days D) 12 days E) 9 days Using CPM, what is the latest finish time for the last activity in this project (i.e., the total time to complete the project)?

A) 10 days
B) 7 days
C) 8 days
D) 12 days
E) 9 days
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
54
A tracking Gantt chart superimposes the current schedule onto a baseline plan so deviations are easily noticed.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
55
If a single estimate of the time required to complete an activity is not reliable, the best procedure is to use a mean and standard deviation (or variance) for each activity.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
56
A simple project listing of five activities, their predecessors, and their respective time estimates are presented here: <strong>A simple project listing of five activities, their predecessors, and their respective time estimates are presented here:   Using the CPM, which activities have slack in this project?</strong> A) A B) B C) C D) D E) C and E Using the CPM, which activities have slack in this project?

A) A
B) B
C) C
D) D
E) C and E
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
57
A project starts out as which of the following?

A) A statement of work
B) Critical path method (CPM)
C) A series of milestones
D) A Gantt chart
E) A latest-start-time estimate
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
58
Currently, there are only two major companies producing project management software, Microsoft, with Microsoft Project, and Primavera, with Primavera Project Planner.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
59
A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here: <strong>A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here:<sub> </sub>   Using CPM, which activities make up the critical path?</strong> A) A, B, D, F, G B) A, C, E, F, G C) A, C, B, F, E D) A, D, E E) None of these choices are correct Using CPM, which activities make up the critical path?

A) A, B, D, F, G
B) A, C, E, F, G
C) A, C, B, F, E
D) A, D, E
E) None of these choices are correct
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
60
You are looking at a chart that has the terms BCWS, BCWP, and AC indicating lines on the chart. What kind of chart are you looking at?

A) Gantt chart
B) PERT chart
C) Bar/milestone chart
D) Total program cost breakdown
E) EVM chart
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
61
For an activity in a CPM analysis, the early finish time is 20 and the late finish time is 20. Which of the following statements is true?

A) The activity's late start must happen before its early start.
B) The activity is on the critical path.
C) The slack for this activity is 20.
D) The duration of this task is zero.
E) The duration of this task is 20.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
62
Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs. <strong>Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs. <sub> </sub>   What are the total time of this project and total normal cost?</strong> A) Total time is 13 days, total cost is $1,200. B) Total time is 12 days, total cost is $1,700. C) Total time is 11 days, total cost is $1,600. D) Total time is 10 days, total cost is $1,750. E) Total time is 9 days, total cost is $1,700. What are the total time of this project and total normal cost?

A) Total time is 13 days, total cost is $1,200.
B) Total time is 12 days, total cost is $1,700.
C) Total time is 11 days, total cost is $1,600.
D) Total time is 10 days, total cost is $1,750.
E) Total time is 9 days, total cost is $1,700.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
63
You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project "direct costs" are given here. <strong>You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project direct costs are given here. <sub> </sub>   The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100. If you crash this project by one day,What is the total (i.e., direct and indirect) project cost?</strong> A) $2,150 B) $2,300 C) $2,400 D) $2,450 E) $2,500 The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100. If you crash this project by one day,What is the total (i.e., direct and indirect) project cost?

A) $2,150
B) $2,300
C) $2,400
D) $2,450
E) $2,500
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
64
A structure for organizing a project where a self-contained team works full time on the project is:

A) pure project
B) modified project
C) functional project
D) hybrid project
E) matrix project
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
65
Popular project management software used in mid-sized projects is

A) Microsoft Word.
B) Microsoft Primavera.
C) Microsoft Project.
D) Microsoft Excel.
E) None of thesechoices are correct
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
66
You have the following time and cost information for use in a time-cost CPM scheduling model. <strong>You have the following time and cost information for use in a time-cost CPM scheduling model.   What are the three costs per unit of time to expedite each activity?</strong> A) A = $300, B = $200, C = $300 B) A = $100, B = $200, C = $400 C) A = $200, B = $200, C = $200 D) A = $100, B = $400, C = $300 E) A = $200, B = $300, C = $400 What are the three costs per unit of time to expedite each activity?

A) A = $300, B = $200, C = $300
B) A = $100, B = $200, C = $400
C) A = $200, B = $200, C = $200
D) A = $100, B = $400, C = $300
E) A = $200, B = $300, C = $400
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
67
In this structure, each project uses people from different functional areas. A dedicated project manager decides what tasks need to be performed and when, but the functional managers control which people to use.

A) Pure project
B) Modified project
C) Functional project
D) Hybrid project
E) Matrix project
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
68
For an activity in a CPM analysis, the early start time is 8 and the late start time is 10. Which of the following statements is true?

A) The late finish is 12.
B) The early finish is 10.
C) The slack for this activity is 2.
D) The duration of this activity is 2.
E) The activity is on the critical path.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
69
A listing of immediate predecessor activities is important information in a CPM analysis for which of the following reasons?

A) It specifies the relationships in the CPM network of activities.
B) It provides useful timing information.
C) It includes cost information.
D) It is the probability information required in the final step of CPM.
E) None of these choices are correct
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
70
In this structure, team members are assigned from the functional units of the organization. The team members remain a part of their functional units and typically are not dedicated to the project.

A) Pure project
B) Modified project
C) Functional project
D) Hybrid project
E) Matrix project
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
71
You know when you have arrived at the optimal solution in using the time-cost CPM scheduling model analysis when what happens?

A) You have found the critical path.
B) You have run out of crash time.
C) You no longer have a linear relationship with costs.
D) You have reached the minimum total cost.
E) You have run out of crash costs.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
72
In CPM analysis, it is generally expected that the relationship between activity direct costs and project indirect costs will be which of the following?

A) Positively related
B) Optimally related
C) Negatively related
D) Not related
E) Fractionally related
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
73
You have just used the network planning model and found the critical path length is 60 days and there are two critical paths. The standard deviation of the first critical path is 10 days and the s.d. of the second critical path is 15 days. The probability that the project will be completed in 70 days or less is equal to (2 decimal accuracy).

A) 0.84
B) 0.25
C) 0.16
D) 0.75
E) 0.66
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
74
A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here: <strong>A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here:<sub> </sub>   Using CPM, which activities have slack in this project?</strong> A) A, B, C B) B, D C) Only C D) C, E E) F, G Using CPM, which activities have slack in this project?

A) A, B, C
B) B, D
C) Only C
D) C, E
E) F, G
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
75
You have just performed a CPM analysis and have found that more than one path through the project network has zero slack values. What can you conclude?

A) You have incorrectly performed the analysis.
B) You have multiple critical paths.
C) Only one path is optimal.
D) More than one path is optimal.
E) The project will not be completed by the desired time.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
76
You have just used the network planning model and found the critical path length is 30 days and the variance of the critical path is 25 days. The probability that the project will be completed in 33 days or less is equal to (2 decimal accuracy).

A) 0.73
B) 0.55
C) 0.12
D) 0.27
E) 0.60
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
77
You have just used the network planning model for a county road resurfacing project and found the critical path length is 40 days and the standard deviation of the critical path is 10 days. Suppose you want to pick a time (in days) within which you will complete the project with 90% confidence level. What should be that time (in days and round to the nearest whole number)?

A) 40
B) 13
C) 37
D) 29
E) 53
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
78
Which of the following is not an advantage of a pure project?

A) The project manager has full authority over the project.
B) Team members report to one boss.
C) A team member can work on several projects.
D) Decisions are made quickly.
E) Team motivation is high.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
79
You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project "direct costs" are given here. <strong>You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project direct costs are given here. <sub> </sub>   The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100. At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs)?</strong> A) 16 days B) 15 days C) 14 days D) 13 days E) 12 days The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100.
At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs)?

A) 16 days
B) 15 days
C) 14 days
D) 13 days
E) 12 days
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
80
Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs. <strong>Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs. <sub> </sub>   If you crash this project to reduce the total time by one day, what is the total time of the project and total cost?</strong> A) Total time is 13 days, total cost is $1,500. B) Total time is 12 days, total cost is $2,000. C) Total time is 12 days, total cost is $2,300. D) Total time is 11 days, total cost is $1,850. E) Total time is 11 days, total cost is $2,350. If you crash this project to reduce the total time by one day, what is the total time of the project and total cost?

A) Total time is 13 days, total cost is $1,500.
B) Total time is 12 days, total cost is $2,000.
C) Total time is 12 days, total cost is $2,300.
D) Total time is 11 days, total cost is $1,850.
E) Total time is 11 days, total cost is $2,350.
Unlock Deck
Unlock for access to all 108 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 108 flashcards in this deck.