Question
The total length of the trench required in a leaching field is determined by

A) effluent quality and the ability of the soil to absorb water from the drain pipes.
B) code requirements.
C) the amount of effluent predicted to be conveyed into the leaching field in a 24-hour period.
D) the results of the percolation test.
Use Space or
up arrow
down arrow
to flip the card.
Question
Anaerobic processes

A) occur when oxygen is deficient.
B) occur in oxygen-rich sewage.
C) do not involve odors.
D) are faster than aerobic processes.
Question
For residential applications, septic tank size is selected based on

A) the number of bathrooms in the building.
B) the estimated number of occupants in the building.
C) the estimated number of hours per day the building is in use.
D) the number of bedrooms in the building.
Question
The outlet of a septic tank should be located 2 inches to 4 inches below the inlet elevation.
Question
The six steps in public water treatment processes are:

A) primary, settling, processing, secondary settling, filtration, and contamination.
B) primary, settling, aeration, filtration, chlorination, and pumping.
C) primary, settling, aeration, secondary settling, filtration, and chlorination.
D) settling, aeration, secondary settling, tertiary settling, filtration, and chlorination.
Question
At least 50' should be between any well and the septic tank or any part of the disposal field.
Question
Sewer pipe should be uniformly supported on undisturbed earth.
Question
Cleanouts are required by most codes at

A) the connection of the building drain and at specified intervals along the sewer line.
B) the connection of the building drain only.
C) specified intervals along the sewer line and at the septic tank.
D) anywhere along the sewer line.
Question
The minimum septic tank size should be equal to the volume of sewage discharged from the building in 24 hours.
Question
Private sewage disposal systems are used for

A) any building that cannot be connected to a public system.
B) residential housing only.
C) back-up for a public system that is overused.
D) commercial buildings only.
Question
What is the first consideration when sizing a septic system?

A) the amount of sewage flow per 24-hour period
B) the size of the septic tank
C) the size of the drainage lines in the leaching fields
D) the size of the seepage pit
Question
A septic tank is a watertight vessel that receives sewage from a building.
Question
Which of these processes occurs last in the public sewage treatment process?

A) settling
B) primary
C) chlorination
D) filtration
Question
The materials in sewage that are inactive solids (and will not become liquids) are called

A) fungi.
B) sludge.
C) effluent.
D) mud.
Question
The slope of the building sewer (sizes through 6 inches) should not be less than 1/8 inch per foot.
Question
The building sewer is located inside the building.
Question
Sewage is

A) the process of breaking down waste.
B) liquid-borne undesirable or questionable material.
C) only organic waste materials.
D) only inorganic waste materials.
Question
The building sewer begins where the sewer line leaves the property.
Question
Septic tanks should be installed as deep as possible to ensure satisfactory performance.
Question
Organic materials are

A) carbon-based compounds.
B) broken down by bacterial action.
C) subject to change and give rise to gases and other chemicals.
D) all of the above.
Question
A thrust block is used to

A) force water to travel against gravity.
B) offset internal forces that can separate joints.
C) hold piping in its proper place in an interior wall.
D) block the flow of water in a pipe.
Question
Using Table 10-1 in the textbook, a 4" diameter pipe can discharge ____________________ gallons per minute with a slope of 1/4" per foot.
Question
Using Table 10-1 in the textbook, a 4" diameter pipe can discharge ____________________ gallons per minute with a slope of 1/8" per foot?
Question
If a thrust block calculation dictates that the required area be equal to 9 square feet, what must be the length of the sides if the thrust block is a square?
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/24
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 10: Sewers Sewage Disposal Methods
1
The total length of the trench required in a leaching field is determined by

A) effluent quality and the ability of the soil to absorb water from the drain pipes.
B) code requirements.
C) the amount of effluent predicted to be conveyed into the leaching field in a 24-hour period.
D) the results of the percolation test.
A
2
Anaerobic processes

A) occur when oxygen is deficient.
B) occur in oxygen-rich sewage.
C) do not involve odors.
D) are faster than aerobic processes.
A
3
For residential applications, septic tank size is selected based on

A) the number of bathrooms in the building.
B) the estimated number of occupants in the building.
C) the estimated number of hours per day the building is in use.
D) the number of bedrooms in the building.
D
4
The outlet of a septic tank should be located 2 inches to 4 inches below the inlet elevation.
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
5
The six steps in public water treatment processes are:

A) primary, settling, processing, secondary settling, filtration, and contamination.
B) primary, settling, aeration, filtration, chlorination, and pumping.
C) primary, settling, aeration, secondary settling, filtration, and chlorination.
D) settling, aeration, secondary settling, tertiary settling, filtration, and chlorination.
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
6
At least 50' should be between any well and the septic tank or any part of the disposal field.
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
7
Sewer pipe should be uniformly supported on undisturbed earth.
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
8
Cleanouts are required by most codes at

A) the connection of the building drain and at specified intervals along the sewer line.
B) the connection of the building drain only.
C) specified intervals along the sewer line and at the septic tank.
D) anywhere along the sewer line.
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
9
The minimum septic tank size should be equal to the volume of sewage discharged from the building in 24 hours.
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
10
Private sewage disposal systems are used for

A) any building that cannot be connected to a public system.
B) residential housing only.
C) back-up for a public system that is overused.
D) commercial buildings only.
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
11
What is the first consideration when sizing a septic system?

A) the amount of sewage flow per 24-hour period
B) the size of the septic tank
C) the size of the drainage lines in the leaching fields
D) the size of the seepage pit
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
12
A septic tank is a watertight vessel that receives sewage from a building.
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
13
Which of these processes occurs last in the public sewage treatment process?

A) settling
B) primary
C) chlorination
D) filtration
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
14
The materials in sewage that are inactive solids (and will not become liquids) are called

A) fungi.
B) sludge.
C) effluent.
D) mud.
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
15
The slope of the building sewer (sizes through 6 inches) should not be less than 1/8 inch per foot.
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
16
The building sewer is located inside the building.
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
17
Sewage is

A) the process of breaking down waste.
B) liquid-borne undesirable or questionable material.
C) only organic waste materials.
D) only inorganic waste materials.
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
18
The building sewer begins where the sewer line leaves the property.
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
19
Septic tanks should be installed as deep as possible to ensure satisfactory performance.
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
20
Organic materials are

A) carbon-based compounds.
B) broken down by bacterial action.
C) subject to change and give rise to gases and other chemicals.
D) all of the above.
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
21
A thrust block is used to

A) force water to travel against gravity.
B) offset internal forces that can separate joints.
C) hold piping in its proper place in an interior wall.
D) block the flow of water in a pipe.
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
22
Using Table 10-1 in the textbook, a 4" diameter pipe can discharge ____________________ gallons per minute with a slope of 1/4" per foot.
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
23
Using Table 10-1 in the textbook, a 4" diameter pipe can discharge ____________________ gallons per minute with a slope of 1/8" per foot?
Unlock Deck
Unlock for access to all 24 flashcards in this deck.
Unlock Deck
k this deck
24
If a thrust block calculation dictates that the required area be equal to 9 square feet, what must be the length of the sides if the thrust block is a square?