Deck 5: Project Management: Planning, Design, and Construction

Full screen (f)
exit full mode
Question
1 The principles of project management include all of the following EXCEPT:

A) Costs
B) Scheduling
C) Event management
D) SMARTER objectives
Use Space or
up arrow
down arrow
to flip the card.
Question
2 What type of chart listed below is typically designed through the use of project management software?

A) Ant Charts
B) Gantt Charts
C) Plant Charts
D) Map Charts
Question
3 The first step in any preliminary planning is:

A) Conducting a Program Analysis and Feasibility Study
B) Commissioning a Planning Committee
C) Select an Architect
D) Developing the Master Plan
Question
4 When conducting a feasibility study, which of the following impacts is considered?

A) Economic Impact
B) Societal Impact
C) Sport Impact
D) All of the Above
Question
5 Which of the following is NOT the responsibility of an architect?

A) Drawing Drafts
B) Building Scale Models
C) Acting as the Main Builder/Renovator for the Facility
D) Aiding is Securing Zoning and Building Permits
Question
6 The ________________ is used to review the major components of the project, market the project to gain financial and general support for the project, and serve as a framework document for the design and construction of the sport facility.

A) Master Plan
B) Program Statement
C) Feasibility Study
D) Timetable
Question
7 Which of the following statements about timelines is TRUE?

A) Contractors are responsible for the creation and management of timetables
B) Timetables are living documents that are always consulted, evaluated, and modified.
C) Items in a timetable are never "fast tracked", regardless of need, environmental situations, or delay.
D) A timetable for design does not affect the design and implementation of management and operations functions.
Question
8 Considerations for site selection include all of the following EXCEPT:

A) Attractiveness of location
B) Natural and environmental conditions
C) Community support
D) None of the Above (i.e., all are considerations)
Question
9 Which of the following is TRUE about the creation of detailed shop drawings for a facility?

A) The architect must work closely with the contractor during this phase to ensure that all essential parts of the facility are included.
B) Shop drawings address all aspect of the facility including appearance, performance aspects, and governing principles.
C) Shop drawings include any modifications, additions, or deletions that have been made based on the recommendations of the architect and/or contractor.
D) All of the Above
Question
10 Throughout the construction process, and especially when construction is nearing completion, the focus turns to the management and operation of the sport facility. Included in this process is all of the following EXCEPT:

A) Preparing the facility management infrastructure.
B) Attracting events to be staged in the facility.
C) Conduct a groundbreaking ceremony.
D) Preparing an event management infrastructure.
Question
Define what would be involved in conducting a feasibility study for a new football facility in a suburban town of your choice.
Question
Develop a program statement for a new golf course.
Question
You have been charged with developing a cost estimate for a renovation to a 50-year old local recreation facility that includes four multipurpose courts, a fitness center, and a swimming pool/aquatic center. What would you include in this estimate?
Question
Create a groundbreaking task timeline for a new multipurpose recreation facility in your hometown by creating a Gantt Chart with Microsoft Project or another project management software.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/14
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 5: Project Management: Planning, Design, and Construction
1
1 The principles of project management include all of the following EXCEPT:

A) Costs
B) Scheduling
C) Event management
D) SMARTER objectives
C
Explanation: Choice C (event management) is not one of the four principles of project management. The four principles are costs, scheduling, quality management, and developing SMARTER objectives.
2
2 What type of chart listed below is typically designed through the use of project management software?

A) Ant Charts
B) Gantt Charts
C) Plant Charts
D) Map Charts
B
Explanation: Choice B (Gantt Chart) is the only correct answer. A Gantt chart is a horizontal bar chart that graphically displays the time relationship of the steps of the project, where each step of the project is represented by a line on the chart indicating the time period to be undertaken. When a Gantt Chart is completed, the sport facility manager can see the minimum total time for each task, the proper sequence of tasks, which tasks are completed at the same time, and which are connected.
3
3 The first step in any preliminary planning is:

A) Conducting a Program Analysis and Feasibility Study
B) Commissioning a Planning Committee
C) Select an Architect
D) Developing the Master Plan
A
Explanation: Choice A (program analysis) because the first step to any preliminary planning is to conduct a review on the need for the facility in terms of the programs that are either already established or are planned to be established, which is normally articulated through the feasibility study. The planning committee (Choice B), architect (Choice C), and master plan (Choice D) cannot be developed or commissioned without this initial information from the program analysis and feasibility study.
4
4 When conducting a feasibility study, which of the following impacts is considered?

A) Economic Impact
B) Societal Impact
C) Sport Impact
D) All of the Above
Unlock Deck
Unlock for access to all 14 flashcards in this deck.
Unlock Deck
k this deck
5
5 Which of the following is NOT the responsibility of an architect?

A) Drawing Drafts
B) Building Scale Models
C) Acting as the Main Builder/Renovator for the Facility
D) Aiding is Securing Zoning and Building Permits
Unlock Deck
Unlock for access to all 14 flashcards in this deck.
Unlock Deck
k this deck
6
6 The ________________ is used to review the major components of the project, market the project to gain financial and general support for the project, and serve as a framework document for the design and construction of the sport facility.

A) Master Plan
B) Program Statement
C) Feasibility Study
D) Timetable
Unlock Deck
Unlock for access to all 14 flashcards in this deck.
Unlock Deck
k this deck
7
7 Which of the following statements about timelines is TRUE?

A) Contractors are responsible for the creation and management of timetables
B) Timetables are living documents that are always consulted, evaluated, and modified.
C) Items in a timetable are never "fast tracked", regardless of need, environmental situations, or delay.
D) A timetable for design does not affect the design and implementation of management and operations functions.
Unlock Deck
Unlock for access to all 14 flashcards in this deck.
Unlock Deck
k this deck
8
8 Considerations for site selection include all of the following EXCEPT:

A) Attractiveness of location
B) Natural and environmental conditions
C) Community support
D) None of the Above (i.e., all are considerations)
Unlock Deck
Unlock for access to all 14 flashcards in this deck.
Unlock Deck
k this deck
9
9 Which of the following is TRUE about the creation of detailed shop drawings for a facility?

A) The architect must work closely with the contractor during this phase to ensure that all essential parts of the facility are included.
B) Shop drawings address all aspect of the facility including appearance, performance aspects, and governing principles.
C) Shop drawings include any modifications, additions, or deletions that have been made based on the recommendations of the architect and/or contractor.
D) All of the Above
Unlock Deck
Unlock for access to all 14 flashcards in this deck.
Unlock Deck
k this deck
10
10 Throughout the construction process, and especially when construction is nearing completion, the focus turns to the management and operation of the sport facility. Included in this process is all of the following EXCEPT:

A) Preparing the facility management infrastructure.
B) Attracting events to be staged in the facility.
C) Conduct a groundbreaking ceremony.
D) Preparing an event management infrastructure.
Unlock Deck
Unlock for access to all 14 flashcards in this deck.
Unlock Deck
k this deck
11
Define what would be involved in conducting a feasibility study for a new football facility in a suburban town of your choice.
Unlock Deck
Unlock for access to all 14 flashcards in this deck.
Unlock Deck
k this deck
12
Develop a program statement for a new golf course.
Unlock Deck
Unlock for access to all 14 flashcards in this deck.
Unlock Deck
k this deck
13
You have been charged with developing a cost estimate for a renovation to a 50-year old local recreation facility that includes four multipurpose courts, a fitness center, and a swimming pool/aquatic center. What would you include in this estimate?
Unlock Deck
Unlock for access to all 14 flashcards in this deck.
Unlock Deck
k this deck
14
Create a groundbreaking task timeline for a new multipurpose recreation facility in your hometown by creating a Gantt Chart with Microsoft Project or another project management software.