Question
Acceleration clauses cannot require a Constructor to perform work in a manner that is more costly than originally planned
Use Space or
up arrow
down arrow
to flip the card.
Question
Generally not included in a Time and Material cost is

A) home office personnel
B) required equipment rental
C) consumed material
D) all of these
Question
For progress billing, the Contract Administrator should coordinate with

A) the Design Professional
B) Subcontractors
C) field supervision
D) all of these
Question
If a Supplier might go bankrupt, the Contract Administrator should

A) get a copy of keys to any storage of materials the Contractor might need
B) have material delivered to the project site or other facility
C) wait for notification of the bankruptcy so no one is pushed into the situation
D) cancel the order and get a new supplier
Question
If there is a ""no damage for delay clause"" the Contract Administrator

A) can relax
B) can thank the Owner
C) should still make sure all delays are documented
D) pursue arbitration related to any delays
Question
If a hazardous substance is exposed

A) the crew should immediately cover it back
B) the crew should notify management and refrain from disturbing it more
C) should stop all work and leave the project site until it is safe and secure
D) should carefully remove it and dispose of it immediately or as soon as possible
Question
When terminating for cause

A) be sure all reasonable efforts to accommodate the performance of the party to be terminated have been documented
B) stop the party to be terminated from performing work immediately upon notice
C) pay any monies due and then terminate the Contractor
D) all of these
Question
Exculpatory clauses

A) usually contain risks that are insurable
B) usually contain risks that are not insurable
C) are illegal
D) are not able to be passed on to a lower-tier party
Question
Indemnity clauses

A) usually contain issues that are insurable
B) usually contain issues that are not insurable
C) are illegal
D) are not able to be passed on to a lower-tier party
Question
Contractors should be alert to hazardous substances in buildings

A) constructed before 1990
B) constructed before 1980
C) constructed before 2000
D) all residences and townhouses regardless of when they were built
Question
It is often said that the most dangerous clause in any Contract is

A) the signature block
B) the one you don't know about
C) the ""Notice Clause""
D) the General Conditions
Question
Constructive Acceleration

A) helps everyone
B) is when the Owner requires the Constructor to increase production without agreeing to pay additional money
C) is determined by the Constructor in counsel with the Subcontractors
D) is usually required based on design errors
Question
Notice clauses can be critical for

A) differing site conditions
B) change orders affecting time and/or money
C) RFI related to an ambiguity
D) all of these
Question
When an Owner exercises a ""Termination for Convenience"" the Constructor is not entitled to any further compensation
Question
An exculpatory clause shifts responsibility for actions done or caused by one party to another party
Question
Contracts can contain indemnity clauses requiring another party to assume the costs for damages done by another party
Question
A Constructor cannot be held responsible for hidden conditions
Question
An Owner cannot delay the whole or a portion of the work without compensating the Constructor
Question
A PRP does not have to be the party or entity that installed the hazardous material
Question
A Contract can be terminated for cause or convenience
Question
UCC stands for Uniform Cost Code
Question
The contract will usually clearly define what will be included in Time and Material costs
Question
In the event of bankruptcy of a Supplier, materials stored at the Supplier's facility become the property of the Contractor
Question
Whether there is a ""notice clause"" or not in the contract, the Contract Administrator should notify the owner of any delays
Question
An Acceleration clause is illegal
Question
A Mechanics Lien is

A) a bad idea
B) a good way to get quick payment
C) also known as a Construction Lien
D) good for an Owner with poor cash flow
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/26
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 7: Killer Clauses
1
Acceleration clauses cannot require a Constructor to perform work in a manner that is more costly than originally planned
False
2
Generally not included in a Time and Material cost is

A) home office personnel
B) required equipment rental
C) consumed material
D) all of these
A
3
For progress billing, the Contract Administrator should coordinate with

A) the Design Professional
B) Subcontractors
C) field supervision
D) all of these
D
4
If a Supplier might go bankrupt, the Contract Administrator should

A) get a copy of keys to any storage of materials the Contractor might need
B) have material delivered to the project site or other facility
C) wait for notification of the bankruptcy so no one is pushed into the situation
D) cancel the order and get a new supplier
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
5
If there is a ""no damage for delay clause"" the Contract Administrator

A) can relax
B) can thank the Owner
C) should still make sure all delays are documented
D) pursue arbitration related to any delays
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
6
If a hazardous substance is exposed

A) the crew should immediately cover it back
B) the crew should notify management and refrain from disturbing it more
C) should stop all work and leave the project site until it is safe and secure
D) should carefully remove it and dispose of it immediately or as soon as possible
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
7
When terminating for cause

A) be sure all reasonable efforts to accommodate the performance of the party to be terminated have been documented
B) stop the party to be terminated from performing work immediately upon notice
C) pay any monies due and then terminate the Contractor
D) all of these
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
8
Exculpatory clauses

A) usually contain risks that are insurable
B) usually contain risks that are not insurable
C) are illegal
D) are not able to be passed on to a lower-tier party
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
9
Indemnity clauses

A) usually contain issues that are insurable
B) usually contain issues that are not insurable
C) are illegal
D) are not able to be passed on to a lower-tier party
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
10
Contractors should be alert to hazardous substances in buildings

A) constructed before 1990
B) constructed before 1980
C) constructed before 2000
D) all residences and townhouses regardless of when they were built
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
11
It is often said that the most dangerous clause in any Contract is

A) the signature block
B) the one you don't know about
C) the ""Notice Clause""
D) the General Conditions
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
12
Constructive Acceleration

A) helps everyone
B) is when the Owner requires the Constructor to increase production without agreeing to pay additional money
C) is determined by the Constructor in counsel with the Subcontractors
D) is usually required based on design errors
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
13
Notice clauses can be critical for

A) differing site conditions
B) change orders affecting time and/or money
C) RFI related to an ambiguity
D) all of these
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
14
When an Owner exercises a ""Termination for Convenience"" the Constructor is not entitled to any further compensation
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
15
An exculpatory clause shifts responsibility for actions done or caused by one party to another party
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
16
Contracts can contain indemnity clauses requiring another party to assume the costs for damages done by another party
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
17
A Constructor cannot be held responsible for hidden conditions
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
18
An Owner cannot delay the whole or a portion of the work without compensating the Constructor
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
19
A PRP does not have to be the party or entity that installed the hazardous material
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
20
A Contract can be terminated for cause or convenience
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
21
UCC stands for Uniform Cost Code
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
22
The contract will usually clearly define what will be included in Time and Material costs
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
23
In the event of bankruptcy of a Supplier, materials stored at the Supplier's facility become the property of the Contractor
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
24
Whether there is a ""notice clause"" or not in the contract, the Contract Administrator should notify the owner of any delays
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
25
An Acceleration clause is illegal
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
26
A Mechanics Lien is

A) a bad idea
B) a good way to get quick payment
C) also known as a Construction Lien
D) good for an Owner with poor cash flow
Unlock Deck
Unlock for access to all 26 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 26 flashcards in this deck.