Deck 5: Emergency Response

Full screen (f)
exit full mode
Question
The IT division of an insurance company in the US has following main on-going activities/projects:
Developing a new web-based tool which will help reduce application processing time by 60%.
Providing application maintenance and support services for existing solution
Call center that answers potential sales leads
The operations are disrupted due to fire in the building resulting in substantial loss of assets. Which of the following operations should be resumed earliest?

A)Development of the new web application
B)Call center answering potential sales leads
C)Providing application support for existing solutions
D)All of the above
E)None of the above
Use Space or
up arrow
down arrow
to flip the card.
Question
What is a secondary risk?

A)A risk that is not that important
B)A risk that is less important
C)Residual risk
D)Risk that is highly unlikely to occur
E)Risk caused by another risk response strategy
Question
A business continuity plan calls for employees to gather at a nearby building that is earthquake safe in event of building collapse due to a seismic event. What is this an example of?

A)Shelter-in-place
B)Hot site
C)Cold-site
D)People first
E)RTO
Question
A leading US based IT hardware company has a key manufacturing base in Thailand. During the 2004 Tsunami, the warehouses of the company situated along the Thai coast were seriously impacted. All of the company's records for orders are stored here. There was no BCP plan in place for what actions to take first in such a dire and unexpected emergency. What should have been the immediate focus area for operations in Thailand?

A)Focus on RTO
B)Focus on RPO
C)Focus on vital equipment and key installations
D)Focus on preserving vital records
E)Safety of employees
Question
As per the project schedule, a team of consultants have to travel to Mexico to implement a new warehouse management product at its manufacturing locations. However, the project manager decides to defer the activity considering a recent flu breakout in the region. This is an example of risk _____________:

A)Reward
B)Sharing
C)Transfer
D)Avoidance
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/5
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 5: Emergency Response
1
The IT division of an insurance company in the US has following main on-going activities/projects:
Developing a new web-based tool which will help reduce application processing time by 60%.
Providing application maintenance and support services for existing solution
Call center that answers potential sales leads
The operations are disrupted due to fire in the building resulting in substantial loss of assets. Which of the following operations should be resumed earliest?

A)Development of the new web application
B)Call center answering potential sales leads
C)Providing application support for existing solutions
D)All of the above
E)None of the above
Providing application support for existing solutions
2
What is a secondary risk?

A)A risk that is not that important
B)A risk that is less important
C)Residual risk
D)Risk that is highly unlikely to occur
E)Risk caused by another risk response strategy
Risk caused by another risk response strategy
3
A business continuity plan calls for employees to gather at a nearby building that is earthquake safe in event of building collapse due to a seismic event. What is this an example of?

A)Shelter-in-place
B)Hot site
C)Cold-site
D)People first
E)RTO
Shelter-in-place
4
A leading US based IT hardware company has a key manufacturing base in Thailand. During the 2004 Tsunami, the warehouses of the company situated along the Thai coast were seriously impacted. All of the company's records for orders are stored here. There was no BCP plan in place for what actions to take first in such a dire and unexpected emergency. What should have been the immediate focus area for operations in Thailand?

A)Focus on RTO
B)Focus on RPO
C)Focus on vital equipment and key installations
D)Focus on preserving vital records
E)Safety of employees
Unlock Deck
Unlock for access to all 5 flashcards in this deck.
Unlock Deck
k this deck
5
As per the project schedule, a team of consultants have to travel to Mexico to implement a new warehouse management product at its manufacturing locations. However, the project manager decides to defer the activity considering a recent flu breakout in the region. This is an example of risk _____________:

A)Reward
B)Sharing
C)Transfer
D)Avoidance