Deck 4: Estimation

Full screen (f)
exit full mode
Question
If the nominal interest rate is 8.2% and the rate of inflation is 6.6%, what is the approximate real interest rate?

A)1.6%
B)7.4%
C)14.8%
D)None of the above
Use Space or
up arrow
down arrow
to flip the card.
Question
What is the estimated labor budget for a 40-week project with the following staffing?
Personnel - Hourly Billing Rate - Hours per Week
Principal --- $185 --- 2
Resident Engineer --- $125 --- 32
Inspector --- $80 --- 40
Administrative Assistant --- $45 --- 10

A)$17,400
B)$151,700
C)$320,800
D)$696,000
Question
What is the calculated overhead rate for an engineering firm that provides inspection and testing services given the following year-end audit information?
Item: Cost ($)
Direct Labor: 922,000
Allowable fringe benefits:452,000
Allowable general overhead: 1,200,000

A)38%
B)156%
C)179%
D)469%
Question
ITE, LLC charges $125/hour for a Resident Engineer (RE) and $75/hour for an Inspector (I). Administrative staff hours are estimated to be 25% of RE and I time and are charged at $45 per hour.
A profit rate of 10% is charged on total labor. If a project is estimated to take 10 weeks, and assuming a 40-hour work week for both the RE and I, what is the estimated marked-up labor cost?

A)$89,000
B)$97,900
C)107,800
D)None of the above
Question
Which of the following best describes the construction cost estimating term stagflation?

A)Slow economic growth, stable inflation and unemployment rates
B)Slow economic growth, increased inflation rates, and relatively high unemployment
C)A. and B.
D)None of the above
Question
What is the sample mean of the following cost data?
Supplier: Cost of Sonar Inspection Unit
CUES:$ 80,000
RedZone: $ 92,500
Olsen Equipment: $ 92,500
Envirosight: $ 100,200
Collins: $ 140,000

A)$80,832
B)$92,500
C)$101,040
D)None of the above
Question
What is the sample median of the following cost data?
Supplier: Cost of Sonar Inspection Unit
CUES:$ 80,000
RedZone: $ 92,500
Olsen Equipment: $ 92,500
Envirosight: $ 100,200
Collins: $ 140,000

A)$80,832
B)$92,500
C)$101,040
D)None of the above
Question
Which of the following is not generally considered a component of construction cost estimate preparation?

A)Preparing planning documents, conceptual drawings, detailed plans, and specifications
B)Interpret technical information and develop estimates of quantities
C)Relate construction specifications and plans to specific site conditions
D)Apply unit price costing that reflects site and current market conditions
Question
In which phase of a typical capital improvement project, such as building a highway or a flood control dam, is cost estimating undertaken?

A)Planning phase
B)Design phase
C)Bidding phase
D)All of the above
Question
Which of the following statements correctly describes a construction cost estimate?

A)Approximation of the probable quantity and unit cost of each element in a project
B)Includes a factor to account for uncertainty and risk associated with project elements and project environment
C)Aggregation of many elements; not a single number
D)All of the above
Question
Which of the following may be considered as an Unforeseen Condition?

A)Contaminated soils
B)Unearthed historic artifact
C)Incorrectly drawn underground utilities
D)All of the above
Question
Which of the following cost estimating techniques is commonly used to develop planning level cost estimates?

A)Analogous
B)Bid-Based
C)Parametric
D)Cost-Based
Question
Which of the following estimating techniques rely on a bottom-up approach to estimate construction costs?

A)Cost-based
B)Bid-based
C)Historical percentages
D)Analogous
Question
The Engineering News-Record (ENR) provides what is considered to be reliable general construction cost index (CCI) and building cost index (BCI) historic values. Which of the following statements best describes the use of ENR indexes?

A)Use CCI when labor costs are a significant portion of total cost
B)Use BCI costs for developing estimates of structures
C)A. and B.
D)None of the above
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/14
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 4: Estimation
1
If the nominal interest rate is 8.2% and the rate of inflation is 6.6%, what is the approximate real interest rate?

A)1.6%
B)7.4%
C)14.8%
D)None of the above
1.6%
2
What is the estimated labor budget for a 40-week project with the following staffing?
Personnel - Hourly Billing Rate - Hours per Week
Principal --- $185 --- 2
Resident Engineer --- $125 --- 32
Inspector --- $80 --- 40
Administrative Assistant --- $45 --- 10

A)$17,400
B)$151,700
C)$320,800
D)$696,000
$320,800
3
What is the calculated overhead rate for an engineering firm that provides inspection and testing services given the following year-end audit information?
Item: Cost ($)
Direct Labor: 922,000
Allowable fringe benefits:452,000
Allowable general overhead: 1,200,000

A)38%
B)156%
C)179%
D)469%
179%
4
ITE, LLC charges $125/hour for a Resident Engineer (RE) and $75/hour for an Inspector (I). Administrative staff hours are estimated to be 25% of RE and I time and are charged at $45 per hour.
A profit rate of 10% is charged on total labor. If a project is estimated to take 10 weeks, and assuming a 40-hour work week for both the RE and I, what is the estimated marked-up labor cost?

A)$89,000
B)$97,900
C)107,800
D)None of the above
Unlock Deck
Unlock for access to all 14 flashcards in this deck.
Unlock Deck
k this deck
5
Which of the following best describes the construction cost estimating term stagflation?

A)Slow economic growth, stable inflation and unemployment rates
B)Slow economic growth, increased inflation rates, and relatively high unemployment
C)A. and B.
D)None of the above
Unlock Deck
Unlock for access to all 14 flashcards in this deck.
Unlock Deck
k this deck
6
What is the sample mean of the following cost data?
Supplier: Cost of Sonar Inspection Unit
CUES:$ 80,000
RedZone: $ 92,500
Olsen Equipment: $ 92,500
Envirosight: $ 100,200
Collins: $ 140,000

A)$80,832
B)$92,500
C)$101,040
D)None of the above
Unlock Deck
Unlock for access to all 14 flashcards in this deck.
Unlock Deck
k this deck
7
What is the sample median of the following cost data?
Supplier: Cost of Sonar Inspection Unit
CUES:$ 80,000
RedZone: $ 92,500
Olsen Equipment: $ 92,500
Envirosight: $ 100,200
Collins: $ 140,000

A)$80,832
B)$92,500
C)$101,040
D)None of the above
Unlock Deck
Unlock for access to all 14 flashcards in this deck.
Unlock Deck
k this deck
8
Which of the following is not generally considered a component of construction cost estimate preparation?

A)Preparing planning documents, conceptual drawings, detailed plans, and specifications
B)Interpret technical information and develop estimates of quantities
C)Relate construction specifications and plans to specific site conditions
D)Apply unit price costing that reflects site and current market conditions
Unlock Deck
Unlock for access to all 14 flashcards in this deck.
Unlock Deck
k this deck
9
In which phase of a typical capital improvement project, such as building a highway or a flood control dam, is cost estimating undertaken?

A)Planning phase
B)Design phase
C)Bidding phase
D)All of the above
Unlock Deck
Unlock for access to all 14 flashcards in this deck.
Unlock Deck
k this deck
10
Which of the following statements correctly describes a construction cost estimate?

A)Approximation of the probable quantity and unit cost of each element in a project
B)Includes a factor to account for uncertainty and risk associated with project elements and project environment
C)Aggregation of many elements; not a single number
D)All of the above
Unlock Deck
Unlock for access to all 14 flashcards in this deck.
Unlock Deck
k this deck
11
Which of the following may be considered as an Unforeseen Condition?

A)Contaminated soils
B)Unearthed historic artifact
C)Incorrectly drawn underground utilities
D)All of the above
Unlock Deck
Unlock for access to all 14 flashcards in this deck.
Unlock Deck
k this deck
12
Which of the following cost estimating techniques is commonly used to develop planning level cost estimates?

A)Analogous
B)Bid-Based
C)Parametric
D)Cost-Based
Unlock Deck
Unlock for access to all 14 flashcards in this deck.
Unlock Deck
k this deck
13
Which of the following estimating techniques rely on a bottom-up approach to estimate construction costs?

A)Cost-based
B)Bid-based
C)Historical percentages
D)Analogous
Unlock Deck
Unlock for access to all 14 flashcards in this deck.
Unlock Deck
k this deck
14
The Engineering News-Record (ENR) provides what is considered to be reliable general construction cost index (CCI) and building cost index (BCI) historic values. Which of the following statements best describes the use of ENR indexes?

A)Use CCI when labor costs are a significant portion of total cost
B)Use BCI costs for developing estimates of structures
C)A. and B.
D)None of the above