Deck 13: Risk and Capital Budgeting
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/90
Play
Full screen (f)
Deck 13: Risk and Capital Budgeting
1
Generally, the higher the coefficient of variation a project has, the higher the discount rate it should be assigned.
True
Explanation: A higher coefficient of variation denotes greater risk, so investors will require a higher rate of return-thus (all else being equal), a "risk-adjusted" rate.
Explanation: A higher coefficient of variation denotes greater risk, so investors will require a higher rate of return-thus (all else being equal), a "risk-adjusted" rate.
2
As the time horizon becomes shorter, more uncertainty enters the forecast.
False
Explanation: The level of uncertainty increases with time.
Explanation: The level of uncertainty increases with time.
3
Simulation models allow the analyst to test possible changes in the variables used in the model.
True
4
Risk is not only measured in terms of losses, but also in terms of variability.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
5
Investment A may have a higher standard deviation than investment B and still have less risk.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
6
A common stock with a beta of 1.0 is said to be of equal risk with the market.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
7
A firm might be willing to accept high risk in a given investment if the portfolio effect (for the whole firm) is beneficial.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
8
Regardless of risk, no projects should be accepted unless they earn more than the firm's weighted average cost of capital.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
9
The standard deviation is the measure of dispersion or variability around the expected value.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
10
The coefficient of correlation represents the standard deviation divided by the expected value.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
11
The equation for the coefficient of variation is (V) =
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
12
The cost of capital is assumed to contain no risk for the firm.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
13
The expected value is a weighted average of the outcomes multiplied by their probabilities of occurrence.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
14
Expected value is defined as ΣDP where the outcomes are D and probabilities are P.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
15
Beta is another measurement of risk and measures the stability of returns on an individual stock relative to the stock market index of returns.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
16
Decision trees present a tabular or graphical comparison of projected decision outcomes.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
17
A basic assumption in financial theory is that most investors and managers are risk seekers.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
18
If we are risk-averse, a risky investment with an 8% return will be preferred over an 8% risk-free investment.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
19
If possible outcomes are D and probabilities are P, the standard deviation is defined as
? =
? =
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
20
As the time horizon increases, the standard deviation for each forecast of cash flow normally increases.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
21
Selection of portfolio combinations from the efficient frontier will depend upon our willingness to assume risk.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
22
When choosing portfolios of assets, management should try to achieve the highest possible return at a given level of risk.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
23
In considering the share price effect on risk-return trade-offs, our goal should always be to earn the highest return possible.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
24
Projects with high positive correlation are sometimes valuable because they allow us to smooth out the overall performance of the firm during a business cycle.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
25
Projects that are totally uncorrelated provide more overall risk reduction than negatively correlated projects.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
26
The highest possible value for positive correlation is +1.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
27
In order to reduce risk, one should diversify into areas that are positively correlated with current areas of involvement.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
28
Assume that Widget Repair Corporation provides services to 100 customers whose decision to change suppliers is uncorrelated. The portfolio effect suggests that the entrepreneur/owner of Widget, who is compensated on the basis of the firm's profits, may have lower cash-flow risk than a clerk who works full-time for Widget on a fixed salary.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
29
Insurance companies take advantage of the portfolio effect by insuring many different homeowners against loss. However, the risks of loss for individual homes in hurricane-prone or earthquake-prone areas such as Florida and California are highly correlated. This suggests that insurance companies should avoid writing (or consider canceling) some customers' policies in Florida and California, even when the policies are both needed by homeowners and expected to be highly profitable to the insurer.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
30
Projects that are totally uncorrelated should provide some overall reduction in portfolio risk.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
31
Cyclical businesses are likely to have higher costs of capital than firms with less variability in earnings. Therefore, more cyclical firms should typically use a higher discount rate in project evaluation.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
32
Sensitivity analysis helps the financial planner determine how sensitive shareholders will be to changes in investment strategy.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
33
The coefficient of variation considers how an investment impacts the total risk of the firm, while the coefficient of correlation considers the specific risk of an investment.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
34
Choosing projects with returns equal to the company norm but having a higher level of risk will most likely lower the company's stock price.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
35
The investor's portfolio should always be on the efficient frontier.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
36
Generally, because of the unpredictability of earnings, cyclical stocks are given higher price-earnings multiples than growth stocks.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
37
The coefficient of variation is calculated to help correlate the standard deviation and the relative expected value of an investment, which makes it easier to compare different sized investments.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
38
The efficient frontier is always along the left-most portion of the risk-return trade-off diagram in which risk is measured on the X-axis and return is measured on the Y-axis.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
39
Combining assets with highly correlated returns will greatly reduce portfolio risk.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
40
The capital budgeting decisions of a firm will have no effect on the share price of the common stock.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
41
In determining the appropriate discount rate for an individual project, the financial manager will be most influenced by the
A) expected value.
B) internal rate of return.
C) standard deviation.
D) coefficient of variation.
A) expected value.
B) internal rate of return.
C) standard deviation.
D) coefficient of variation.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
42
If three investment alternatives all have some degree of risk and different expected returns, which of the following measures could best be used to rank the risk levels of the projects?
A) The coefficient of correlation
B) The coefficient of variation
C) The standard deviation of returns
D) The net present value
A) The coefficient of correlation
B) The coefficient of variation
C) The standard deviation of returns
D) The net present value
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
43
The standard deviation can be defined as
A)
B)
C)
D)
A)
B)
C)
D)
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
44
A project has the following projected outcomes in dollars: $250, $350, and $500. The probabilities of their outcomes are 25%, 50%, and 25%, respectively. What is the expected value of these outcomes?
A) $362.5
B) $89.4
C) $94.5
D) $178.3
A) $362.5
B) $89.4
C) $94.5
D) $178.3
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
45
Which of the following is a characteristic of beta?
A) Beta measures only the volatility of returns on an individual bond relative to a bond market index.
B) A beta of 1.0 has zero risk.
C) A beta of less than 1.0 has less risk than the market.
D) A beta is always equal to 1.0.
A) Beta measures only the volatility of returns on an individual bond relative to a bond market index.
B) A beta of 1.0 has zero risk.
C) A beta of less than 1.0 has less risk than the market.
D) A beta is always equal to 1.0.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
46
If one project has a higher standard deviation than another,
A) it may have a lower risk.
B) it may have a lower expected value.
C) it has fewer possible outcomes.
D) it may be riskier, but this can only be determined by the coefficient of variation.
A) it may have a lower risk.
B) it may have a lower expected value.
C) it has fewer possible outcomes.
D) it may be riskier, but this can only be determined by the coefficient of variation.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
47
A project's cash flows have a beta of 1.2, a standard deviation of $340, and a coefficient of variation of 0.40. What is the expected cash flow?
A) $850
B) $167
C) $2,400
D) $500
A) $850
B) $167
C) $2,400
D) $500
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
48
The coefficient of variation (V) can be defined as the
A) expected value multiplied by the standard deviation.
B) standard deviation divided by the mean (expected value).
C) mean (expected value) divided by the standard deviation.
D) standard deviation squared, divided by the expected value.
A) expected value multiplied by the standard deviation.
B) standard deviation divided by the mean (expected value).
C) mean (expected value) divided by the standard deviation.
D) standard deviation squared, divided by the expected value.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
49
Buchanan Corp. forecasts the following payoffs from a project:
What is the expected value of the outcomes?
A) $5,000
B) $4,000
C) $5,300
D) The forecast is incorrect and must be modified before finding the expected value.
What is the expected value of the outcomes?
A) $5,000
B) $4,000
C) $5,300
D) The forecast is incorrect and must be modified before finding the expected value.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
50
A project's coefficient of variation is 0.55. The project has a positive coefficient of correlation of 0.20. The expected value is $1,200. What is the standard deviation?
A) $400
B) $220
C) $660
D) $1,200
A) $400
B) $220
C) $660
D) $1,200
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
51
An investment with a $500 standard deviation and a $5,000 expected value has a higher risk than an investment with a $4,000 standard deviation and a $50,000 expected value.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
52
The term "risk-averse" means that
A) an individual refuses to take risks.
B) most investors and businessmen seek risk.
C) an individual will seek to avoid risk or be compensated with a higher return.
D) only investment proposals with no risk should be accepted.
A) an individual refuses to take risks.
B) most investors and businessmen seek risk.
C) an individual will seek to avoid risk or be compensated with a higher return.
D) only investment proposals with no risk should be accepted.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
53
Investors tend to decrease required rates of return over time for projects with longer lives.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
54
Firm X is considering a project and its analysts have projected the following outcomes and their probabilities.
What is the expected value of the outcomes?
A) $3,375
B) $8,633
C) $8,265
D) Cannot be determined. Depends upon which prediction is correct.
What is the expected value of the outcomes?
A) $3,375
B) $8,633
C) $8,265
D) Cannot be determined. Depends upon which prediction is correct.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
55
The measure of risk is best described as
A) potential loss.
B) the variability of outcomes around some expected value.
C) the probability of expected values.
D) the potential expected loss.
A) potential loss.
B) the variability of outcomes around some expected value.
C) the probability of expected values.
D) the potential expected loss.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
56
Which of the following is a false statement?
A) Risky investments may produce large losses.
B) Risky investments may produce large gains.
C) The coefficient of variation is a risk measure.
D) Risk-averse investors cannot be induced to invest in risky assets.
A) Risky investments may produce large losses.
B) Risky investments may produce large gains.
C) The coefficient of variation is a risk measure.
D) Risk-averse investors cannot be induced to invest in risky assets.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
57
The concept of being risk-averse means
A) investors don't want to take on any risk.
B) investors would usually prefer investments with high standard deviations and a greater opportunity for gain.
C) that the greater the risk, the lower the expected return must be.
D) that for a given situation, investors would prefer relative certainty to uncertainty, and the greater the risk, the higher the expected return must be.
A) investors don't want to take on any risk.
B) investors would usually prefer investments with high standard deviations and a greater opportunity for gain.
C) that the greater the risk, the lower the expected return must be.
D) that for a given situation, investors would prefer relative certainty to uncertainty, and the greater the risk, the higher the expected return must be.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
58
The higher the risk of an investment, the lower the required rate of return by investors.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
59
Modigliani and Associates has forecasted the following payoffs from a project:
What is the expected value of the outcomes?
A) $0
B) $3,300
C) $3,700
D) Cannot be determined. Depends upon which prediction is correct.
What is the expected value of the outcomes?
A) $0
B) $3,300
C) $3,700
D) Cannot be determined. Depends upon which prediction is correct.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
60
Which investment has the least amount of risk?
A) Standard deviation = $450, expected return = $4,500
B) Standard deviation = $600, expected return = $400
C) Standard deviation = $500, expected return = $800
D) Standard deviation = $400, expected return = $5,000
A) Standard deviation = $450, expected return = $4,500
B) Standard deviation = $600, expected return = $400
C) Standard deviation = $500, expected return = $800
D) Standard deviation = $400, expected return = $5,000
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
61
Which ways can a decision tree be presented to help lay out the sequence of decisions that can be made?
A) Tabular
B) Graphical
C) A and B
D) None of these options are correct.
A) Tabular
B) Graphical
C) A and B
D) None of these options are correct.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
62
An example of negative correlation may exist between the
A) forest products and housing industries.
B) jewelry and discount furniture industries.
C) steel and aluminum industries.
D) oil and auto industries.
A) forest products and housing industries.
B) jewelry and discount furniture industries.
C) steel and aluminum industries.
D) oil and auto industries.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
63
Place the following investment decisions in order from the lowest risk to the highest risk:
(a) purchase of replacement machinery
(b) new product in a foreign market
(c) new product in the local market
(d) repair of existing machinery
A) b, c, a, d
B) d, a, b, c
C) d, b, a, c
D) d, a, c, b
(a) purchase of replacement machinery
(b) new product in a foreign market
(c) new product in the local market
(d) repair of existing machinery
A) b, c, a, d
B) d, a, b, c
C) d, b, a, c
D) d, a, c, b
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
64
Risk may be integrated into capital budgeting decisions by
A) adjusting the standard deviation of possible outcomes.
B) determining the expected value.
C) adjusting the discount rate.
D) adjusting the time horizon.
A) adjusting the standard deviation of possible outcomes.
B) determining the expected value.
C) adjusting the discount rate.
D) adjusting the time horizon.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
65
Simulation models allow the planner to
A) reduce the standard deviations of projects.
B) plan ahead for all possible changes in each variable.
C) deal with the uncertainty of investment risk.
D) test possible changes in each variable and deal with the uncertainty in forecasting outcomes.
A) reduce the standard deviations of projects.
B) plan ahead for all possible changes in each variable.
C) deal with the uncertainty of investment risk.
D) test possible changes in each variable and deal with the uncertainty in forecasting outcomes.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
66
Using the risk-adjusted discount rate approach, projects with high coefficients of variation will have ________ net present values than projects with low coefficients of variation and similar cash flows.
A) somewhat higher
B) substantially higher
C) lower
D) either somewhat higher or substantially higher
A) somewhat higher
B) substantially higher
C) lower
D) either somewhat higher or substantially higher
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
67
A correlation coefficient of zero indicates
A) the projects have the same expected value.
B) there is no correlation and no risk reduction when the projects are combined.
C) there is no correlation, but there is some risk reduction when the projects are combined.
D) the projects have the same standard deviation.
A) the projects have the same expected value.
B) there is no correlation and no risk reduction when the projects are combined.
C) there is no correlation, but there is some risk reduction when the projects are combined.
D) the projects have the same standard deviation.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
68
The coefficient of correlation
A) takes on values anywhere from 0 to +1.
B) takes on values anywhere from −1 to 0.
C) takes on values anywhere from −1 to +1.
D) takes on values of 0 or larger.
A) takes on values anywhere from 0 to +1.
B) takes on values anywhere from −1 to 0.
C) takes on values anywhere from −1 to +1.
D) takes on values of 0 or larger.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
69
Which investment has the least amount of risk?
A) Coefficient of variation = 8%, expected return = $800
B) Coefficient of variation = 8%, standard deviation = $200
C) Standard deviation = $300, expected return = $5,000
D) Standard deviation = $100, expected return = $80
A) Coefficient of variation = 8%, expected return = $800
B) Coefficient of variation = 8%, standard deviation = $200
C) Standard deviation = $300, expected return = $5,000
D) Standard deviation = $100, expected return = $80
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
70
The firm's highest risk-adjusted discount should be applied to
A) the repair of old machinery.
B) a new product in a related field.
C) a new product in a foreign market.
D) the purchase of new equipment.
A) the repair of old machinery.
B) a new product in a related field.
C) a new product in a foreign market.
D) the purchase of new equipment.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
71
In order to reduce risk in a firm, the firm would seek to enter a business that
A) has a high positive correlation with its present business.
B) has a zero correlation with its present business.
C) has a high negative correlation with its present business.
D) has a high negative variation with its present business.
A) has a high positive correlation with its present business.
B) has a zero correlation with its present business.
C) has a high negative correlation with its present business.
D) has a high negative variation with its present business.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
72
A "what if" simulation using a computer helps to
A) reduce the risk associated with a particular investment.
B) determine the effects of changes in certain variables.
C) increase the accuracy of the inputs.
D) make data entry more complicated.
A) reduce the risk associated with a particular investment.
B) determine the effects of changes in certain variables.
C) increase the accuracy of the inputs.
D) make data entry more complicated.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
73
Using the risk-adjusted discount rate approach, the firm's weighted average cost of capital is applied to projects with
A) no risk.
B) low risk.
C) normal risk.
D) high risk.
A) no risk.
B) low risk.
C) normal risk.
D) high risk.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
74
The lower the coefficient of correlation, the greater the
A) risk when projects are combined.
B) risk reduction when projects are combined.
C) return when projects are combined.
D) standard deviation when projects are combined.
A) risk when projects are combined.
B) risk reduction when projects are combined.
C) return when projects are combined.
D) standard deviation when projects are combined.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
75
Portfolio risk is evaluated differently than individual project risk. In evaluating portfolio risk, we
A) need to consider the impact of a given project on the overall risk of the firm.
B) recognize that a risky investment may create a portfolio with less risk.
C) need to consider how the returns of the projects in the portfolio are correlated.
D) all of these options are true.
A) need to consider the impact of a given project on the overall risk of the firm.
B) recognize that a risky investment may create a portfolio with less risk.
C) need to consider how the returns of the projects in the portfolio are correlated.
D) all of these options are true.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
76
A Monte Carlo simulation model uses
A) random variables as inputs.
B) a point estimate.
C) the cost of capital.
D) portfolio risk.
A) random variables as inputs.
B) a point estimate.
C) the cost of capital.
D) portfolio risk.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
77
Which of the following is a common approach in dealing with uncertainty?
A) A Monte Carlo simulation
B) An internal rate of return
C) The net present value
D) Beta
A) A Monte Carlo simulation
B) An internal rate of return
C) The net present value
D) Beta
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
78
The "portfolio effect" in capital budgeting refers to
A) the relationship of stocks to bonds.
B) the degree of correlation between various investments.
C) the coefficient of variation.
D) the risk-adjusted discount rate.
A) the relationship of stocks to bonds.
B) the degree of correlation between various investments.
C) the coefficient of variation.
D) the risk-adjusted discount rate.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
79
A tool that helps to organize the decision process by presenting a graphical comparison of investment choices is called a
A) module hierarchy diagram.
B) "what if" simulation.
C) decision tree.
D) None of these options are correct.
A) module hierarchy diagram.
B) "what if" simulation.
C) decision tree.
D) None of these options are correct.
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck
80
In order to evaluate risk, management may also set qualitative risk classes. Rank these four projects from least risky to most risky, all other things being equal.
1) Completely new market in United States.
2) Completely new market in South America.
3) Addition to normal product line.
4) Repair to old machinery.
A) 4, 3, 1, 2
B) 1, 2, 3, 4
C) 3, 4, 1, 2
D) 4, 3, 2, 1
1) Completely new market in United States.
2) Completely new market in South America.
3) Addition to normal product line.
4) Repair to old machinery.
A) 4, 3, 1, 2
B) 1, 2, 3, 4
C) 3, 4, 1, 2
D) 4, 3, 2, 1
Unlock Deck
Unlock for access to all 90 flashcards in this deck.
Unlock Deck
k this deck

