Every documented requested change must be either accepted or rejected by an authority from the project management team; the proper authority is called a ________.
A) project management committee
B) change control board
C) change management database
D) change control matrix
Correct Answer:
Verified
Q39: In the time management knowledge area, the
Q40: The downside to using a formal process
Q41: A key tool used as input for
Q42: In configuration management, this is recording and
Q43: In configuration management process, this is identifying
Q45: _ and control involves a set of
Q46: With respect to monitoring and control, which
Q47: In configuration management, this is the release
Q48: Estimate at completion (EAC) is equal to
Q49: The integrated _ control process is a