This is the budgeted cost for the work scheduled to be completed on a task, work package, or activity up to a given point in time. Also referred to as budgeted cost of work scheduled (BCWS) .
A) EV
B) AV
C) AC
D) PV
Correct Answer:
Verified
Q57: These numbers are related to resource time
Q58: Schedule variance (SV) equals earned value (EV)
Q59: Monitoring and control processes are used to
Q60: Cost performance index (CPI) equals the ratio
Q61: _ (which happens during IT projects when
Q63: In configuration management, this is validating the
Q64: The _ control process is responsible for
Q65: This is the revised estimate for the
Q66: The _ management knowledge area includes processes
Q67: The process of verifying scope is responsible