The first step in the risk management planning process is to ________ as many risks as possible for the upcoming project, with the knowledge that you can never see them all.
A) analyze
B) identify
C) document
D) eliminate
Correct Answer:
Verified
Q42: A key benefit of this technique is
Q43: Risk management protects against invisible transfers of
Q44: This is an explanation of the strategy
Q45: There are risks that provide new opportunities
Q46: The _ technique is another technique that
Q48: Which of the following is NOT a
Q49: A project manager's objective is not to
Q50: _ is a non-structured or semi-structured method
Q51: Risk management sets up projects for success
Q52: The PMBOK defines risk management as "the