________ task dependencies are based on work performed by an entity outside the organization or business unit.
A) Mandatory
B) Discretionary
C) External
D) Project
Correct Answer:
Verified
Q40: Function point analysis can be done at
Q41: _ is defined as the actual amount
Q42: _ task dependencies are defined based on
Q43: _ is defined as the amount of
Q44: The precedence diagram method (PDM) of constructing
Q46: Time and cost estimates should be done
Q47: Sunken costs are all costs incurred over
Q48: The final deliverable from the activity sequencing
Q49: The activity definition process identifies the lowest
Q50: The _ process is concerned with determining