The Determination of a Weak to Strong Matrix Structure Is

Question 49

Multiple Choice

The determination of a weak to strong matrix structure is primarily determined by:


A) Whether the project manager is assigned to the project full-time or part-time.
B) The level of authority granted to the project manager.
C) The level of authority granted to project team members.
D) Both A and B