The First Step in the Creation of a PERT/CPM Chart

Question 19

Multiple Choice

The first step in the creation of a PERT/CPM chart is to ____.


A) determine the logical order of project tasks
B) identify the graphical planning aids to use
C) identify all the project tasks
D) determine the status of all tasks

Correct Answer: