The first step in the creation of a PERT/CPM chart is to ____.
A) determine the logical order of project tasks
B) identify the graphical planning aids to use
C) identify all the project tasks
D) determine the status of all tasks
Correct Answer:
Verified
Q14: In a PERT/CPM chart, each task has
Q15: A _ path includes all tasks that
Q16: A(n) _ chart displays complex task patterns
Q17: In addition to tasks, every project has
Q18: PERT/CPM is called a(n) _ technique, because
Q20: For a project manager, reporting _.
A)involves controlling
Q21: Microsoft claims that Microsoft Project has the
Q22: Problems with timetables and project milestones can
Q23: Microsoft's risk management model includes _.
A)category, which
Q24: A risk _ plan is a proactive