MATCHING
Identify the letter of the choice that best matches the phrase or definition.
a.project management
f.weight
b.project coordinator
g.bottom-up technique
c.project leader
h.dependent
d.milestone
i.concurrent
e.constraint
j.predecessor
-In discussing PERT/CPM charts, you discuss the types of task patterns that can occur in a project schedule. You give an example of two tasks, A and B, that can both begin as soon as task C is finished. Which of the following is NOT a true statement about tasks A and B?
A) They are predecessor tasks of each other.
B) They are concurrent tasks.
C) They each depend on task C.
D) They are multiple successor tasks of task C.
Correct Answer:
Verified
Q73: Matching
Identify the letters of the choices that
Q102: MATCHING
Identify the letter of the choice that
Q103: MATCHING
Identify the letter of the choice that
Q105: MATCHING
Identify the letter of the choice that
Q106: MATCHING
Identify the letter of the choice that
Q107: MATCHING
Identify the letter of the choice that
Q108: MATCHING
Identify the letter of the choice that
Q109: MATCHING
Identify the letter of the choice that
Q111: MATCHING
Identify the letter of the choice that
Q112: MATCHING
Identify the letter of the choice that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents