Metro City would like a pedestrian bridge constructed across Big Creek.The city will accept bids on the project until a specified date.Bidders must submit a bid bond that guarantees if the bid is accepted,the bidder will sign the construction contract and furnish a bond that guarantees the construction work will be completed according to contract specifications.This second bond the bidder must post is a
A) performance bond.
B) payment bond.
C) maintenance bond.
D) completion bond.
Correct Answer:
Verified
Q25: Two tellers of a Tenth National Bank
Q26: State X hired Build-Right Construction to build
Q27: State X hired Build-Right Construction to build
Q28: Al's Electric Service is an electric contracting
Q29: A cashier at Food World Supermarket accepted
Q31: A bond that guarantees that the person
Q32: Insurer A began to provide crime insurance
Q33: Graham is a cashier at a convenience
Q34: State X hired Build-Right Construction to build
Q35: Which of the following statements is (are)true
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents