The principal advantage a Gantt chart has over other project scheduling techniques is:
A) its ability to reveal relationships among activities.
B) it illustrates multiple paths as a project network.
C) it focuses on the critical path.
D) its simplicity.
E) both cost and time are included in the chart.
Correct Answer:
Verified
Q57: Project planning determines how the project is
Q58: Which of the following is not involved
Q59: Quality tools such as control charts can
Q60: The main determinant of the way PERT/CPM
Q61: In the probabilistic approach to precedence network
Q63: The project management technique that is repeated
Q64: A relatively simple tool for planning and
Q65: There are four activities on the critical
Q66: A PERT/CPM activity has an optimistic duration
Q67: Concerning PERT and CPM,which of the following
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents