Which of the following is not an advantage(s) the PERT/CPM technique has over a Gantt chart?
A) its ability to reveal relationships among activities.
B) it illustrates multiple paths as a project network.
C) it indicates which activities are most critical.
D) it indicates the implications of delays in activities.
E) it is a more complex scheduling system.
Correct Answer:
Verified
Q72: Which of the following is not an
Q73: Given this information about activity B: ES
Q74: Activity 4 in a network diagram has
Q75: Activity 7 is directly preceded by two
Q76: Besides project activities,the primary information that all
Q78: Which of the following is not a
Q79: When developing probabilistic estimates of project duration,it
Q79: Activity C has an early start time
Q81: Which of the following is not an
Q82: The owner of Ace Building Co.is about
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents