The Project Manager is about to begin a project comprised of the following six activities: What is the estimated standard deviation of the duration for activity E?
A) 2 days
B) 3 days
C) 4 days
D) 16 days
E) 24 days
Correct Answer:
Verified
Q94: A project manager for Durable Construction Co.is
Q95: Uncontrolled growth in the number of activities
Q96: The Project Manager is about to begin
Q97: At which point does crashing of a
Q98: In "crashing",a project manager will generally focus
Q100: The owner of Ace Building Co.is about
Q101: The manager of a National Forest is
Q102: A project superintendent is about to begin
Q103: Activity E has an optimistic duration of
Q104: The manager of a National Forest is