The frequency of breakdown of a piece of equipment is 2.55 breakdowns per month.The cost of a breakdown is $1,000 and the cost of preventive maintenance is $2,000 per month.Assume that the equipment breakdown can be avoided if preventive maintenance is performed.Should the manager use preventive maintenance,or would it be better to fix the equipment when it breaks down?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q7: Maintenance activities are often organized into the
Q17: Maintenance activities are often organized into the
Q19: Factors affecting the decision of how much
Q21: When breakdowns become frequent and/or costly,managers are
Q22: Ideally,preventive maintenance will be performed:
A)after a planned
Q23: "Total productive maintenance" is best described as:
A)avoiding
Q25: The average time before breakdown of a
Q26: The type of maintenance which is reactive
Q27: Reliability-centered maintenance is an approach based on:
A)dealing
Q59: The goal of maintenance is to maintain
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents